Performance Measurement Generate Codes (tpppc5500m000)
Use this session to list data of a generate code.
Field Information
- Project
-
The project code.
- Generate Code
-
The generated codes store information about the generation of performance measurement data.
- Baseline
-
The baseline used for the generation.
- Version
-
The version used for the generation.
- Date to
-
The date up to which the analysis is performed.
- Budget Type
-
The budget type for which performance measurement generate code is defined.Note: By default, this field is set to Top Down.
Allowed values
- Top Down
-
Calculating the cost or sales amount in a top down structure means you distribute a top amount to the lower level elements. There is no aggregation of the costs. The structural element you work from determines the amount. The rule is that LN looks for amounts on estimate lines on level Total/Cost Type/Other Structure/Detail and in that order.
- Bottom Up
-
Calculating the cost or sales amount in a bottom up structure means you give exact amounts for lowest level elements and aggregate them to make the top amount.
- Budget Cost Analysis Version
- The budget cost analysis version for which performance measurement generate code is defined.