Print Physical Progress Form by Activity/Cost Object (tpppc1423m000)
Use this session to print progress details for a combination of activity and cost object. You can then use this form for recording details on-site.
You can enter the current/latest progress in the work center manually, either daily or weekly, and re-enter them later into the relevant session.
Field Information
- Material
 - 
            
If this check box is selected, LN prints progress for the item cost object.
 - Labor
 - 
            
If this check box is selected, LN prints progress for the labor cost object.
 - Equipment
 - 
            
If this check box is selected, LN prints progress for the equipment cost object.
 - Subcontracting
 - 
            
If this check box is selected, LN prints progress for the subcontracting cost object.
 - Sundry Cost
 - 
            
If this check box is selected, LN prints progress for the sundry cost cost object.