Procedure Status (tppdm6584m000)
Use this session to view and maintain the project procedure status.
Field Information
- Project
 - 
            
The project procedure code.
 - Description
 - 
            
The description or name of the code.
 - Project Status
 - 
            
The status of the project.
Allowed values
- Free
 - Active
 - Finished
 - Closed
 - Archived
 
 - Description
 - 
            
The description or name of the code.
 - 
            
- Status
 - 
              
The status of the following procedures :
- Update Work Authorization Status (tppss2205m000)
 - Update Budget Status (tpptc2201m000)
 - Create/Update Baseline (tppss2220m000)
 - Generate Control Data (tpptc1230m000)
 - Generate Budget from Reference Activity (tpptc2250m000)
 - Generate Budget Cost Analysis (tpptc3200m000)
 - Generate Service Orders (tppss6250m000)
 - Generate Planned PRP Orders (tppss6200m000)
 - Approve Planned PRP Purchase Orders (tppss6220m000)
 - Transfer Planned PRP Purchase Orders (tppss6230m000)
 - Approve Planned PRP Warehouse Orders (tppss6225m000)
 - Transfer Planned PRP Warehouse Orders (tppss6235m000)
 
 - Automatic
 - 
              
If this check box is selected, LN automatically links the steps to the project procedure.
 - 
              
- Step
 - 
                
The next step of the procedure.
 - Order Information
 - 
                
Displays the order information.