Copy Estimate Lines (tpest1205m000)
Use this session to copy a range of estimate lines within the same version, to another version, or from one project/version to another project/version.
The application skips:
- Estimate lines with estimate type Top Down.
 
When you copy across projects, LN will skip:
- Estimate lines with project-related cost objects that are not available in the target project.
 - Estimate lines with PCS items whose "derived from item" is not available in the Item - Project (tppdm0105s000) session.
 
Field Information
- 
            
- Project
 - 
              
The code that identifies the project.
 - Project Status
 - 
              
- Free
 - Active
 - Finished
 - Closed
 - Archived
 
 - Version
 - Version
 - 
              
The status of the estimate version.
 - Lines
 - 
              
The From line number.
 - Estimate Lines Selection
 - 
              
The To line number.
 
 - 
            
- Project
 - 
              
The code that identifies the project.
 - Project Status
 - 
              
- Free
 - Active
 - Finished
 - Closed
 - Archived
 
 - Version
 - Version
 - 
              
The status of the estimate version.
 
 - 
            
- Delete Structure Data
 - 
              
If this check box is selected, all structure data of the copied lines will be removed.
If this check box is cleared, the following applies:
- The primary structure of the source and target version must be of the same structure type.
 - The structure elements of the source must be available in the target primary structure.
 
If these conditions are not met, structure data will be removed from the lines.
 - Process Report
 - 
              
If this check box is selected, LN prints the process report for the specified data.
 - Error Report
 - 
              
If this check box is selected, LN prints the error report for the specified data.