Call-Offs (tpctm6103m000)
Use this session to view the list of call-off lines for each scope line.
Note:
- This session is displayed only if the Scope Of Work check box is selected in the Contract Lines (tpctm1110m000) session.
- The call off lines can only be created for a scope line if the Call-Off check box is selected in the specific scope line in the Scope Document Lines (tpctm6601m000) session.
- When the Call-Off Line is created after AFP is generated, the status of the scope line is set to Modified in the Scope Document Lines (tpctm6601m000) session.
- When the new call-off line created and scope is active, that must be added to the AFP lines that are not yet processed.
Field Information
- Call-Off Line
- The call-off line number.
- Creation Date
- The date and time when the Call-Off Line is created.
- Quantity
-
The quantity of the call-off associated with the scope.
Note: If the Line Type field is set to the Quantity and Rate option, the call-off quantity must not exceed the scope line quantity.
- Unit
- The unit in which the call-off Quantity is expressed.
- Customer Reference Number
- The code of the customer reference number for each scope line, provided for the tracking purposes.
- Modified
-
Indicates whether the related scope document line data is modified.
- Start Date On-Site
-
The date and time from when the call-off period starts at the site.
Note: This value is defaulted from the Scope Document Lines (tpctm6601m000) session.
- End Date On-Site
-
The date and time when the call-off period ends at the site.
Note: The value in this field can be used as the basis for specifying the rate when variations are introduced.