Call-Offs (tpctm6103m000)

Use this session to view the list of call-off lines for each scope line.

Note: 
  • This session is displayed only if the Scope Of Work check box is selected in the Contract Lines (tpctm1110m000) session.
  • The call off lines can only be created for a scope line if the Call-Off check box is selected in the specific scope line in the Scope Document Lines (tpctm6601m000) session.
  • When the Call-Off Line is created after AFP is generated, the status of the scope line is set to Modified in the Scope Document Lines (tpctm6601m000) session.
  • When the new call-off line created and scope is active, that must be added to the AFP lines that are not yet processed.

Field Information

Call-Off Line
The call-off line number.
Creation Date
The date and time when the Call-Off Line is created.
Quantity
The quantity of the call-off associated with the scope.
Note: If the Line Type field is set to the Quantity and Rate option, the call-off quantity must not exceed the scope line quantity.
Unit
The unit in which the call-off Quantity is expressed.
Customer Reference Number
The code of the customer reference number for each scope line, provided for the tracking purposes.
Modified

Indicates whether the related scope document line data is modified.

Start Date On-Site
The date and time from when the call-off period starts at the site.
Note: This value is defaulted from the Scope Document Lines (tpctm6601m000) session.
End Date On-Site
The date and time when the call-off period ends at the site.
Note: The value in this field can be used as the basis for specifying the rate when variations are introduced.