Using the External Scheduling Interface
You can use the External Scheduling Interface (tppss2231m000) session to export a project to the external scheduling package (ESP). A XML file is used to export the data. Note You can also import a project to the LN application, using a XML file, after you optimize the planning process in the respective scheduling package.
You can also use this session to:
- Import or export multiple projects from or to an external scheduling package.
 - Only export the calendars defined in these sessions: 
            
- Calendars for External Packages (tcccp0181m000)
 - Employees (tccom0501m000)
 - Trade Groups (tppdm0530m000)
 - Equipment (tppdm0112s000)
 
 
The options available in the session are:
- Export
 - Activities and Budget Lines (Tasks)
 - Project Cost Objects and Standard Costs Objects (Resources)
 - Assignments (Budget Lines)