tirpt domains
- Confirm
 - 
           
Sets the order status from Planned to Confirmed. You can only do this if the order type is INA or RRP.
 - None
 - 
           
No Help topic is associated with this item.
 - Release
 - 
           
Sets the order status to Released. You can only do this if the order type is JSC.
 - Report
 - 
           
Sets the order status to Completed.
 - Transfer
 - 
           
Sets the order status to Planned. You can only do this if the order type is INA or RRP. The order type becomes JSC.
 
- At Reporting Complete
 - At Completing Shift
 - At Closing Work Cell Cost Document
 - Manual
 
- Day
 - Not Applicable
 - Week
 - 4 Weeks
 - Month
 
- Amount per labor hour
 - 
           
The surcharge is expressed as a fixed amount per work hour. The duration of the shifts and work days influences the total surcharge.
 - Amount per Work Cell hour
 - 
           
The surcharge is expressed as a fixed amount per work cell hour. The availability of the work cell influences the total surcharge.
 - Fixed amount per shift
 - 
           
The surcharge expressed as a fixed amount per shift. The amount can be positive or negative and is not influenced by the duration of the shift.
 
- None
 - 
           
You do not report the operation as complete. The operation status is not changed.
 - All in Period
 - 
           
You report the operation as complete for the quantities that are equal to or greater than the minimum quantity that can be reported as complete.
 
- Manual
 - 
           
You have to manually report the schedule line competed in the Report Shift (tirpt4636m200) session.
 - Automatic
 - 
           
Schedule line status is set to completed, when ordered quantity is reached.
 
- Open
 - 
           
Costs can be added to the cost document.
 - Closed
 - 
           
Costs can no longer be added to the cost document.
 - Initial
 - 
           
The cost document has been generated, but no costs have been added.
 
- Estimated
 - Registered
 - Actual Initialized
 - Actual Approved
 - Posted to People
 
- Based on Production Schedules
 - Based on Start Dates
 
- On Schedule
 - Early
 - Lagging
 
- Planning
 - 
           
The production run is scheduled using Enterprise Planning .
 - Manual
 - 
           
The production run is scheduled manually.
 
- Free
 - 
           
Run schedule is controlled by the planning engine.
 - Firm
 - 
           
- The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the enterprise planning or other planning engines.
 - Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
 
 - Released
 - 
           
Run schedule complete, changes can only be made manually.
 - Active
 - 
           
Production run schedule is being implemented.
 - Production Completed
 - 
           
All schedule lines for the production run were completed, but the run has not been closed.
 - Completed
 - 
           
All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.
 - Closed
 - 
           
The run schedule was completed, changes can no longer be made.
 
- Not Applicable
 - In Repair
 - 
           
The items is being reworked at the repair cell.
 - Sent to Warehouse
 - 
           
The item was repaired and is send to the warehouse specified in the original schedule line instead of being returned to the line.
Note: Warehouse orders are not updated or activated. When the repair schedule line is completed, the related warehouse order lines are deleted. - Sent Back to Work Cell
 - 
           
The item was repaired and will be returned to the schedule line it was rejected from.
Note: It is not possible to send a repaired item back to the schedule line if the line was reported completed. 
- Set Up
 - Run
 - Down
 - Wait
 
- Single-Product
 - 
           
Used to maintain production models for the manufacture of a single end item.
 - Multi-Product
 - 
           
Used to maintain production models for the manufacture of multiple end items in different quantities.
 
- Item
 - 
           
The production schedules are directly connected to a repetitive item.
 - Scheduling Area
 - 
           
The production schedules are connected to a repetitive item via the scheduling area and the routing of the item.
 
- Planned
 - 
           
All production order data can still be changed.
 - Order Documents Printed
 - 
           
The documents that accompany the production order are printed.
 - Released
 - 
           
The production order is released for production.
 - Active
 - 
           
Work on the production order has started.
 - To be Completed
 - 
           
The order is reported with the Completed status.
 - Completed
 - 
           
The order is reported with the Completed status and all completed products are delivered to inventory.
 
- Preventive
 - Breakdown
 - Phase-in
 - Phase-out
 
- RRP
 - 
           
An order that originates from the Enterprise Planning package.
 - SIC
 - 
           
An order that originates from the Warehousing package.
 - JSC
 - 
           
An order that originates from the Job Shop Control module.
 
- Open
 - 
           
The shift is still in progress, work is being done on the work list in the Work List (tirpt4602m000) session.
 - Completed
 - 
           
The shift has ended.
 - Closed
 - 
           
The shift has ended, backflushing has taken place and cost documents are closed.
 
- In Stock
 - The material shortage or availability check is performed based on the On Hand quantity.
 - Planned Available
 - The material availability or shortage check is performed based on the Planned Receipts quantity.
 
- Supply Warehouse
 - 
           The check for material shortage or availability includes the main Warehouse and Point of Usage (POU).
           Note: POU must be included in the Enterprise Planning.
 - Warehouses in Site
 - 
           The check for material shortage or availability includes all Warehouses with or without EP check.
           Note: To exclude Warehouses without EP, you can select the Planned Warehouse Only check box.
 - Warehouses in Cluster
 - 
           The check for material shortage or availability includes all Warehouses that are linked to the same Cluster, with or without EP check.
           Note: To exclude Warehouses without EP, you can select the Planned Warehouse Only check box.
 
- Show Items with Shortage
 - Only Items with a shortage are displayed.
 - Show all Items
 - All Items with and without shortage are displayed.
 
- By Line
 - The materials shortage check is performed based on each Production Schedule Line.
 - By Run
 - The materials shortage check is performed based on Production Schedule Lines that have the same Run ID.