Material Costs by Cost Component (tirpt7520m000)
Use this session to view the cost for the items associated with a cost document.
Field Information
- Site
 - 
            
The site ID.
Note: Only visible if multisite functionality is active. - Cost Document
 - 
            
The work cell cost document number for which the material is costed.
 - Production Model Status
 - 
            
The status of the production model.
Allowed values
- New
 - Approved
 - Expired
 
 - Start Date
 - 
            
The cost document start and end date and time.
 - Work Cell
 - 
            
The work cell for which the cost document is maintained.
 - Calculation Date
 - 
            
The date on which the costs are calculated.
 - Material
 - 
            
The material used for production.
 - Cost Component
 - 
            
The code of the cost component linked to the item of the work cell cost document.
 - Estimated Cost
 - 
            
The estimated material cost of the product.
 - Registered Cost
 - 
            
The material costs of the product manufactured in the period the cost document has been active.
 - Expected Cost
 - 
            
The material costs expected by the end of the cost document period.
 - Actual Cost
 - 
            
The actual material costs registered from the start of the cost document.
 - Estimated Quantity
 - 
            
The estimated quantity of items required to complete the operation.
 - Registered Quantity
 - 
            
The part of the estimated quantity that has been reported completed.
 - Expected Quantity
 - 
            
The quantity of product expected to be manufactured.
 - Actual Quantity
 - 
            
The actual quantity of items required to complete the operation.
 - Estimated Hours
 - 
            
The estimated number of production hours required to complete the operation.
 - Registered Hours
 - 
            
Part of the estimated hours that have been used for manufacture.
 - Expected Hours
 - 
            
The estimated hours still free for use.
 - Actual Hours
 - 
            
The actual number of production hours required to complete the operation.