Close Production Schedules (tirpt4201m000)
Use this session to close a range of production schedule (lines).
           Note: This session validates the status of material lines in the selected production order lines for the production schedule.
          
         Field Information
- Site
 - 
            
The site ID.
Note: Only visible if multisite functionality is active. - Production Schedule
 - 
            
The ID of the schedule.
Note: The value is defaulted from the Production Schedules (tirpt4101m000) session. - Schedule Position
 - 
            
The ID of the production schedule line.
Note: The value is defaulted from the Production Schedule Lines (tirpt4102m000) session. - Schedule Lines Only
 - 
            
If this check box is selected, the open material lines for the selected range of production schedule lines are closed.