Schedule Line Work Stations (tirpt4111m000)
Use this session to view the work stations linked to the work cell of the production schedule line.
- The Report on Work Stations check box in the Repetitive Manufacturing Parameters (tirpt0100m000) session must be selected to use this session.
 - The schedule line must have the status Released.
 - The Quarantine Inventory check box in the Inventory Handling Parameters (whinh0100m000) session must be selected to use the quarantine options in this session.
 
Field Information
- Production Schedule
 - 
            
The production schedule ID.
 - Schedule Position
 - 
            
The line position in the schedule.
Allowed values
- Free
 - 
              
Run schedule is controlled by the planning engine.
 - Firm
 - 
              
- The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the enterprise planning or other planning engines.
 - Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
 
 - Released
 - 
              
Run schedule complete, changes can only be made manually.
 - Active
 - 
              
Production run schedule is being implemented.
 - Production Completed
 - 
              
All schedule lines for the production run were completed, but the run has not been closed.
 - Completed
 - 
              
All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.
 - Closed
 - 
              
The run schedule was completed, changes can no longer be made.
 
 - End Item
 - Work Cell
 - Status
 - 
            
Production line status.
Allowed values
- Free
 - 
              
Run schedule is controlled by the planning engine.
 - Firm
 - 
              
- The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the enterprise planning or other planning engines.
 - Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
 
 - Released
 - 
              
Run schedule complete, changes can only be made manually.
 - Active
 - 
              
Production run schedule is being implemented.
 - Production Completed
 - 
              
All schedule lines for the production run were completed, but the run has not been closed.
 - Completed
 - 
              
All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.
 - Closed
 - 
              
The run schedule was completed, changes can no longer be made.
 
 - Scheduled Start Date
 - 
            
The date and time manufacture on the schedule line starts.
 - Work Station
 - 
            
The work station that is part of the work cell.
 - Station Position
 - 
            
The position of the work station in the work cell structure.
 - Work Station Is Count Point
 - 
            
If this check box is selected, the work station is a count point.
 - Work Station is Inspection Point
 - 
            
If this check box is selected, the work station is an inspection point.
Note: Only applicable if the Report on Work Stations check box in the Production Model (tirpt2100m100) session is selected for the product model. - Quantity Rejected
 - The total quantity that is rejected during production for the schedule line.