Print Activities (tipcs4401m000)
Use this session to print activities.
Field Information
- Project
 - Project Manager
 - 
            
The person that is in charge of the project.
 - Status
 - 
            
Indicates the current progress of the project.
 - Start Date
 - 
            
The date the project is started.
 - End Date
 - 
            
The date the project is completed.
 - Activity
 - 
            
The activity in the network planning for a project.
 - Search Key
 - Activity Manager
 - Earliest Start Date
 - 
            
The earliest date the activity is started.
 - Activity Schedule
 - 
            
If this check box is selected, LN prints the activity schedule. You can select the start date, the scale factor, and the type of start date for printing the activity schedule.
 - Start Date
 - 
            
Enter the start date of the activity schedule.
 - Scale Factor
 - 
            
Enter the scale factor for the activity schedule.
Example
1: one scale section is 1 day 5: one scale section is 5 days  - Type of Start Date
 - 
            
Select a type of start date to display activities on the planning board.
 - Details
 - 
            
If this check box is selected, LN prints a detailed report.
 - Also Completed Activities
 - 
            
If this check box is selected, LN prints all activities including those that are completed.
 - Activity Texts
 - 
            
If this check box is selected, LN prints the text belonging to activities created with the Activities (tipcs4101m000) session.
 - Job Sheet by Activity
 - 
            
You can chose to print Job Sheet sorted by Activity.
Allowed values
- Yes
 - No
 
 - Sort by
 - 
            
You can chose to sort date by:
Allowed values
- Project
 - Work Center
 - Activity Manager