Replace Item in Production Bills of Material (timfc3210m300)
Use this session to replace an item for multiple Production BOMs with a new material item for a range of products.
Note: This session can only be accessed if the Job Shop by Siteconcept is set to Active in the Implemented Software Components (tccom0100s000) session.
Field Information
- Change Note
-
- Selection
-
Indicate if the change is to be performed on a new or existing change note.
Note:- By default, the value is set to New.
- The New option is displayed only if the Change Notes Active check box is selected in the Product Engineering Parameters (timfc0100m000) session.
Allowed values
- New
- A new change number is generated.
- Add to Note
- The change is added to an existing change note.
- Not Applicable
- Change Note
-
The code of the change note.
Note: This field is displayed only if the Change Notes Active check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- Reason
-
The reason for the change.
Note:
- This field is displayed only if the Change Notes Active check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- This value cannot be modified.
- New Revision
-
- Effective Date
- The date and time from when the change is effective.
- Target BOMs
-
- Material
- The code of the item that is replaced.
- From Product
- The range of products which the production BOMs with the selected material that is replaced.
- Replacement Data
-
- Replacement Item
- The code of the new item.
- Use Up Inventory
- If this check box is selected, the current available inventory is used before the issue of the replacement item.
- Options
-
- Approve New Revision
- If this check box is selected, the new revision is approved.
- Simulate
-
If this check box is selected, the change is not processed, however, a report of the revisions that are to be changed, is generated.
Note: By default, this check box is selected.
- Print Process Report
-
If this check box is selected, a report is printed when the process is completed.