Use Up and Alternative Materials by Engineering BOM (tiedm2115m000)
Use this session to maintain the use-up materials and alternative materials for the materials in an engineering BOM (E-BOM) .
To change the priority of an alternative material, select the alternative-material line and click or
Field Information
- Engineering Item
 - Engineering Item Revision
 - 
            
The engineering item's revision.
 - Status
 - 
            
The status of the revision.
 - Unit
 - BOM Quantity
 - EBOM Position
 - 
            
The position number of the EBOM line.
This is equivalent to the position number of a PBOM, except there is no sequence number. A sequence number defines items that are valid on different dates. Revisions can carry out that (of defining items that are valid on different dates) function for engineering items.
 - Component
 - 
            
The component of the engineering item (E-item) revision. The component can be either an E-item or a standard item.
 - Position
 - 
            
Identification of the alternative-material record.
 - Alternative Priority
 - 
            
The alternative priority determines which of the alternatives LN will select first.
Allowed values
- 
              
Use up
This is an outdated material ( use-up material) that must be used up first. - 
              
1
The alternative that will be selected if the inventory of the standard material (and the use-up material, if any) is insufficient. - 
              
2
The alternative that will be selected if the inventory of the standard material and the first alternative material (and the use-up material, if any) is insufficient. - 
              
3, 4, 5, ...
Lower priority alternative materials. - 
              
9
The lowest priority alternative material. 
 - 
              
 - Alt. Component Type
 - 
            
The alternative material's component type ( Item or E-Item).
 - Alternative Item
 - 
            
The alternative material.
Note:You can select a non-configurable item only as an alternative.
For more information on procuring purchased configurable items, refer to
- Procuring configured items in Assembly Control - Master Data Setup