Alternative Estimated Materials (ticst0150m000)
Use this session to view the use-up materials and alternative materials linked to the estimated materials.
You cannot modify the data in this session.
To modify the alternatives defined for an estimated material, execute the following steps:
- Change the alternative materials linked to the lines of the bill of material (BOM). For detailed information, refer to Defining alternative materials.
 - Then, run the Generate Alternatives for Estimated Materials (ticst0216m000) session.
 
Field Information
- Production Order
 - Position
 - 
            
The component's position number in the Estimated Materials (ticst0101m000) sesion.
 - Site
 - 
            
The site ID.
 - Alternative
 - 
            
Identification of the alternative-material record.
 - Alternative Priority
 - 
            
The alternative priority determines which of the alternatives LN will select first.
Allowed values
- 
              
Use up
This is an outdated material ( use-up material) that must be used up first. - 
              
Original
The standard item. - 
              
1
The alternative that will be selected if the inventory of the standard material (and the use-up material, if any) is insufficient. - 
              
2
The alternative that will be selected if the inventory of the standard material and the first alternative material (and the use-up material, if any) is insufficient. - 
              
3, 4, 5, ...
Lower priority alternative materials. - 
              
9
The lowest priority alternative material. 
 - 
              
 - Alternative Item
 - 
            
The alternative material.