Subcontracting Procurement Order Line Call-Offs (tdpur6103m000)
Use this session to maintain the Call-Offs for the subcontracting procurement order lines.
Note:
- This session can be accessed only if:
- TheServices Procurement Orders check box is selected in the Procurement Parameters (tdpur0100m000) session.
- The Subcontracting Procurement Orders check box is selected in the Procurement Parameters (tdpur0100m000) session.
- The Project (TP) check box is selected in the Implemented Software Components (tccom0100s000) session.
- You can modify the data in this session only if the subcontracting procurement Order Status is set to a value other than Canceled or Closed.
- The subcontracting procurement order can be deleted only if the subcontracting procurement Order Status is set to Created.
Field Information
- Subcontracting Procurement Order
-
The code for subcontracting procurement order.
Note:
- The field is defaulted from the service procurement order series.
- The application uses this sequence to default the series for the Subcontracting Procurement Order:
- The series specified in the Subcontracting Order field in the Services Procurement Order Type (tdpur0692m000) session.
- The series specified in the subcontracting procurement Series field in the Procurement User Profiles (tdpur0143m000) session.
- The series specified in the subcontracting procurement Subcontracting Procurement Order Series field in the Purchase Offices (tdpur0112m000) session.
- Line
-
The Subcontracting Procurement Order line number.
Note: The field is enabled only if the Line Type field is set to Rate Only.
- Sequence
-
The line number detail of the subcontracting procurement order.
Note: The field is enabled only if the Line Type field is set to Rate Only.
- Variation Line
- The variation line number of the subcontracting procurement order line.
- Call-Off Line
- The Call-off line number of the subcontracting procurement order line.
- Call-Off Quantity
- The Call-Off Quantity of the subcontracting procurement order line.
- Quantity Unit
-
The unit in which the quantity is expressed.
Note:
- This field is enabled and mandatory only if Call-Off Quantity is specified.
- The unit is valid only if a conversion factor between the unit and the base unit exists for Subcontracted Service, the Base Unit is Quantity Unit or the Time Unit, based on the Cost Determination field.
- Procurement Rate
- The rate at which goods and services are purchased by an organization.
- The currency in which the order amount is expressed.
- Procurement Rate Unit
-
The unit of measure for the procurement rate.
Note:
- This field is enabled only if:
- The Line Type field is set to other than
- The Description Only check box is cleared.
- This value is defaulted from the subcontracting procurement order line if the Line Type is and Call Off lines exist.
- This value cannot be modified if the Line Type field is set to Quantity and Rate.
- The unit is valid only if a conversion factor between the unit and the base unit exists for subcontracting, the Base Unit is the Time Unit for Line Type, Quantity and Rate.
- This field is enabled only if:
- Effective Procurement Rate
-
The effective rate at which goods and services are purchased by an organization.
Note: When multiple procurement rates exists for a subcontracting procurement rate, the effective rate is displayed based on the Start Date On-Site of the call-off line.
- Currency
- The currency in which the amounts on the purchase contract are expressed.
- Call-Off Amount
- The amount on which the Call-Off calculation is based.
- Net Amount
- The net amount of the Subcontracting Procurement Order.
- Modified
- Indicates if the Subcontracting Procurement Order line is modified.
- Start Date On-Site
-
Indicates the date and time when the period for subcontracting or the hiring starts.
Note: This value is defaulted from the Subcontracting Procurement Order (tdpur6600m000) session.
- End Date at Site
-
Indicates the date by when the period for subcontracting or the hiring ends.
Note: This value is defaulted from the Subcontracting Procurement Order (tdpur6600m000) session.
- Creation Date
- The date on which the Subcontracting Procurement Order line is created.
- Scope of Work
-
The scope of work specified for the Subcontracting Procurement Order.
Note:
- This field is enabled only if the Description Only check box is cleared.
- The Line Type must be , , or .
- If the Nature of Supply type is , you can select an item only of the type.
- The value specified for the Services Trade of the subcontracting procurement order must be the same as the Services Trade of the selected subcontracted service.
- Line Type
-
Indicates how the cost amount of the order line amount is retrieved.
Allowed values
- Amount Only
- Rate Only
- Quantity and Rate
- Not Applicable
- Capped Amount
-
Indicates the maximum amount that can be invoiced for the order line.
Note: The field is enabled if the Line Type field is set to .
- Assessed Quantity
- The subcontracting procurement order quantity assessed.
- Remaining Quantity
-
The remaining quantity after deducting Applied Quantity Previous Periods from the Ordered quantity.
Formula: Remaining Quantity = Ordered quantity – Applied Quantity Previous Periods.
- Assessed Amount
- The amount for the assessed services.
- Remaining Amount
-
The remaining amount to the previous period.
Formula: Remaining Amount = Ordered Amount – Applied Amount Previous Periods
. - Order Discount %
- The discount percentage applicable on the released retention amount.
- Discount Amount
- The discount amount applicable on the released retention amount.