Cost Mappings (tcmcs0149m000)
Use this session to link cost components to standard cost objects.
For each newly created cost component, LN adds a line with cost type No Mapping.
           Note: This session is available only if the Project Pegging check box is selected in the Implemented Software Components (tccom0100s000) session.
          
         Field Information
- Cost Component
 - Sequence Number
 - Cost Type
 - 
            
The logistic cost type that is linked to the cost component.
 - Project Cost Type
 - 
            
            
Default value: No Mapping
 - Cost Object
 - Effective Date
 - Expiry Date
 - Log Zero Amounts
 - 
            
If this check box is selected, LN logs the project cost transactions of the cost component of which the transaction amount is zero.
Note: If this check box is selected, the number of transactions registered in the Cost Transactions (tpppc2100m000) session increase and the performance of the CPU is affected.