Item Actual Landed Costs (tclct3600m000)

Use this session to view actual landed costs by item.

Prices by Cost Component

The lines on this tab refer to the Item Actual Landed Costs by Cost Component (tclct3501m000) session, in which you can view an item's actual landed costs by cost component.

Note: 
  • Together with the average purchase price, the average landed cost is used to determine an item's standard cost.
  • This session is updated when all landed costs for a purchase receipt are invoiced. If the invoice is unapproved, the cost calculation for the average landed cost is reversed.
  • Prices are only updated if all invoices for all landed cost lines related to a receipt have the Update Average/Last Purchase Price check box selected.
  • The Landed Cost - Product Subcontracting section is displayed only if the Subcontracting with Material Flow check box is selected in the Implemented Software Components (tccom0100s000) session..

Field Information

Item

item

Latest Landed Cost Transaction Date

The most recent date on which the item's landed cost was changed.

Cumulative Purchase Receipts

The quantity of cumulative receipts based on which the average landed cost is calculated.

Note: You can reset the cumulative purchase receipts in the Equate Balance of Receipts with Inventory Level (tdipu0201m000) session.
Purchase Price Unit

purchase price unit

Note: When the purchase price unit is changed, prices are automatically recalculated.
Total Average Landed Cost

The total of all linked cost components ' average landed cost. The average landed cost is based on cumulative purchases or on the current inventory, as specified in the Method of Calculating Average Landed Cost field of the Landed Costs Parameters (tclct0100m000) session.

Currency

purchase currency

Total Latest Landed Cost

The total of all linked cost components' latest landed cost.

Landed Cost - Product Subcontracting
Latest Landed Cost Transaction Date
The latest date on which the landed cost of the subcontracted product has changed.
Total Average Landed Cost
The total of the average landed cost of the linked cost components. This value is based on cumulative purchases or the current inventory, as specified in the Method of Calculating Average Landed Cost - Product Subcontracting field of the Landed Costs Parameters (tclct0100m000) session.
Total Latest Landed Cost
The total of the landed cost of the linked cost components.
Cumulative Purchase Receipts
The quantity of the cumulative purchase receipts based on which the average landed cost is calculated for the subcontracted product. This value is expressed in the purchase price unit.