Creating a Subcontractor Variation Request (SVR)
- Click the Initiate Variation Request option on the Subcontracting Procurement Order page.
 - Click Yes in the Confirmation window that is displayed.
 - Review this information:
           
- Original subcontracting procurement order
 - The code of the subcontracting procurement order for which the variation request is initiated.
 - Project
 - The code of the project linked to the subcontracting procurement order.
 - Service trade
 - The code of the service trade.
 - Original net amount
 - The total amount for the order.
 - Contractor proposed net amount
 - The amount proposed by the contractor.
 - Subcontractor proposed net amount
 - The amount proposed by the subcontractor.
 - Agreed net amount
 - The amount that is agreed by the contractor and the subcontractor.
 
 - Specify this information:
           
- Nature of Variation
 - 
              Indicates if the variation can be recovered. Possible values:
              
- Recoverable
 - Non-Recoverable
 
 - Reason code
 - The reason code. This code is defaulted from Infor LN.
 - Change reason
 - The description for the change in the scope of work.
 
 - Click Save. The header information is saved.
 - Click Lines. The Variation lines page is displayed.
 - Modify the value or add a new line for the variation request.
           Note: You can decrease the value for a line only if the value in the variation line field is greater than 0.
 - Click Save. The status of the variation request is set to In Process.
           Note: The subcontractor can modify the value for the variation request before clicking the Submit option.
 - Click Submit. The variation request is sent to the contractor for approval