Scheduling Constraints (plsch2160m000)

Use this session to view the constraints encountered by the Scheduling Engine.

Field Information

Scenario
The code of the scenario.
Scheduling Constraint ID
The ID of the scheduling constraint.
Production Order
The code of the production order for which the scheduling constraint is defined.
Operation Block
The code of the operation block.
Resource Type

The type of resource used for the production order operation.

Allowed values

Not Applicable
Machine
Employee
Tool
Site
The code of the site linked to the production order.
Work Center
The code of the work center linked to the production order.
Machine Type
The code of the machine capacity group.
Machine
The code of the machine required for the order.
Employee
The user name of the employee.
Tool
The code of the tool required for the order.
Tool Number
A unique number assigned to the tool.
Item
The code of the item to be produced.
Previous Operation
The code of the previous operation performed for the specific scenario.
Constraint Type

The type of constraint encountered during scheduling.

Allowed values

Machine
Work cannot be performed because the required machine is not available.
Employee
Work cannot be performed because the concerned employee is not available.
Tool
Work cannot be performed because the tool that is required is not available.
Predecessor
Work cannot be performed because one of the production operation order step's predecessor is not completed.
Subassembly
Work cannot be performed because the required subassembly is not available.
Delayed/Postponed Statuses
Work cannot be performed because the production operation order status is set to Delayed or Postponed and the order cannot start.
Purchased Item
Work cannot be performed because the necessary raw material is not available.
Perish between Operations
Work cannot be performed because the maximum perishability value in of an operation is exceeded.
Perish within Operation
Work cannot be performed because the maximum perishability value between indivisible operations is exceeded.
Fixed Buffer
Work could not start when it is scheduled because of the value of the parameter:
  • SCH_DynBufDefault
Dynamic Buffer
Work cannot be performed because of the value of the dynamic buffer specified for the machine.
Transfer Time
Work cannot be performed because of the transfer time specified for the operation for which the operation order step is generated. Transfer time is the time taken to transfer to the next operation.
Raw Material
Work cannot be performed because the necessary raw material is not available.
Start Date
Delay
Delay Unit

...

Allowed values

Seconds
Minutes
Hours
Days
Weeks
Sequence