Scenarios (plsch0101m000)

Use this session to view and maintain scenarios. You can use a scenario to perform these actions:

  • Extract data from LN
  • Run the scheduling engine to synchronize data with LN
  • Stop the scheduling engine in case of any technical glitches
  • Update the production orders in LN

Field Information

Scenario
The code of the scenario.
Active

Indicates if the scenario is Active.

Status

The status of the scenario.

Allowed values

Initial
Running
Completed
Failed
Schedule Start Date
The date and time when the scheduling engine is run.
Detailed Logging

...

Run By
The user who runs the scheduling engine.
Integration Date
Path
The location at which the data can be extracted.
Run/Progression
Run Number
Scheduling Engine Progress
System Parameters
Detail Schedule Duration
Detail Schedule Duration Unit

...

Allowed values

Seconds
Minutes
Hours
Days
Weeks
Minimum Duration of Inactive Periods
Inactive Period Unit

...

Allowed values

Seconds
Minutes
Hours
Days
Weeks
Period to Compare Production Order Steps
Period to Compare Production Order Steps Unit

...

Allowed values

Seconds
Minutes
Hours
Days
Weeks
Earliest starting time for Postponed Production orders
Unit Earliest starting time for Postponed Production orders

...

Allowed values

Seconds
Minutes
Hours
Days
Weeks
Selected Date

...

Allowed values

Planned Dates
Leveled Dates
Max Transfer Lot
Forecasting Scope
Second Forecasting Scope
Apply Dynamic Buffer

...

Compress / Expansion

...

Load Forecast Receipts

...

Use Inactivity Periods

...

Use of Following Resources

...

Generate Schedule Constraints

...

Weight Parameters
Consistent Dispatching
Minimize Cycle Time
Respect of Gradation (General)
Respect of Gradation (Machine)
Just-in-Time Production
Machine Production Rate
Minimize Setups (General)
Minimize Setups (Machine)
Reduction of Time Losses