Supply Order (plaps3601m000)
Use this session to view a supply order.
Field Information
- Scenario
 - The code of the scenario.
 - Supply Order Type
 - 
            
The type of supply order.
Allowed values
- Warehouse Supply Order
 - Purchase Order
 - Distribution Order
 - Manufacturing Order
 - Substitution Order
 - PRP Purchase Order
 - PRP Warehouse Order
 - Project
 
 - Order
 - The name of the supply order.
 - Plan Item
 - The code of plan item. The code consists of the cluster code, the project code, and the item code.
 - Plan Item
 - The code of plan item. The code consists of the cluster code, the project code, and the item code.
 - Quantity
 - The required quantity of the plan item.
 - General
 - 
            
- Actual Date
 - The actual date and time when the supply order is completed.
 - Due Date
 - The date and time by when the supply order must be completed.
 - Lateness
 - The duration by which the order is delayed.
 - Actual Start Date
 - The date and time when the supply order is started.
 - Transaction
 - The transaction number of the supply order.
 - Calculated Due Start Date
 - The start date calculated based on the based on the due date.
 - Quantity Supplied
 - The total quantity supplied.
 - CO Percent
 - The customer order percentage of the supply order.
 - WO Percent
 - The work order percentage of the supply order.
 - Total Quantity
 - The total quantity supplied.
 - Supplying Transaction
 - The code of the supply transaction.
 - Supply Order Transaction
 - The code of the supply transaction.
 - Calculated Planning Start Date
 - The date and time by when the supply order must be started. The start date is calculated based on the previous supply order.
 - Calculated Planning End Date
 - The date and time by when the supply order must be completed. The end date is calculated based on the previous supply order and calculated planning start date.
 - Calculated Status
 - 
              
The status of the supply order.
Allowed values
- Planned
 - Firm Planned
 - Confirmed
 - Released
 
 - Recommended Date
 - The proposal date for supply order. The REQ engine generates the recommended date for the firm planned, confirmed and released supply orders based on the infinite capacity plan.
 - Due Requirement Date
 - The date and time by when customer require a product to be shipped.
 - Actual Requirement Date
 - The actual date and time when the customer shipped the product.
 - Number of RCM
 - The total number of recommendations.
 - Due Start Date
 - The date and time by when the supply order must be started.
 - Planned Start Date
 - The planned date and time by when the supply order must be started.
 - Planned End Date
 - The planned date and time by when the supply order must be completed.
 - Quantity In Process
 - The quantity of a product that is currently being processed in a phase of the production.
 - Status
 - 
              
The status of the supply order.
Allowed values
- Planned
 - Firm Planned
 - Confirmed
 - Released
 
 - Planning Priority
 - 
              
The process of determining the order in which tasks must be completed to maximize productivity and efficiency.
Allowed values
- Maximum
 - Very High
 - High
 - Medium High
 - Medium
 - Medium Low
 - Low
 - Very Low
 - Minimum
 
 - User Priority
 - 
              
The priority of the user for supply order. The priority level set manually by the user.
Allowed values
- Maximum
 - Very High
 - High
 - Medium High
 - Medium
 - Medium Low
 - Low
 - Very Low
 - Minimum
 
 - Target Date
 - The date and time generated by the Requirements Engine based on target inventory replenishment.
 - Phantom SO Step
 - The supply order step for the phantom item.
 - Phantom Planned Supply Order
 - The planned supply order number of the phantom item.
 - Planned Requirement Date
 - The date and time by when the components or material is required for production.
 - Due Finish Date
 - The date and time by when the supply order transaction must be completed.
 - Planned Finish Date
 - The planned date and time by when the supply order transaction must be completed.
 - Actual Finish Date
 - The actual date and time when the supply order transaction is completed.
 - Recommended Date Lateness
 - The date and time agreed for the delay in the start date. The date agreed between planned start date and actual start date.
 - Comment
 - The information related to the recommended date lateness.
 - Purchase Price
 - The amount paid for a purchased item.
 - Planned Date
 - The date and time when the supply order is planned.
 - Changed Delivery Date
 - The new delivery date that is used if the supplier cannot comply with the agreed delivery date and states a new delivery date.
 - Confirmed Delivery Date
 - The delivery date for the supply orders, which is confirmed by the buy-from business partner or confirmed to the sold-to business partner.
 - Planned Delivery Date
 - The date on which the supply order is expected to arrive in the destination warehouse.
 
 - Transfer Time
 - The planned wait time between two operations.
 - Quantity To Ship
 - The number of units of a supply order that are to be shipped to business partner.
 - Propagation Type
 - 
            
The type of propagation.
Allowed values
- No Propagation
 - Propagation Add and Changes
 - Propagate Changes
 
 - Actual Buyer
 - The employee who is the contact to the concerned buy-from business partner.
 - Actual Buyer
 - The employee who is the contact to the concerned buy-from business partner.
 - Actual Planner
 - The employee or department responsible for planning the production, purchase and distribution of items.
 - Supplier Ship From
 - The origin or location from which a supplier ships their products or goods to a business or customer.
 - Supplier Ship From
 - The origin or location from which a supplier ships their products or goods to a business or customer.
 - Supplier Buy From
 - The business partner from whom you order goods or services.
 - Plan Item Distribution Origin
 - The origin or starting point of the item distribution.
 - Plan Item Substitute For
 - The alternative item that can replace a specific material in bill of materials.
 - BOM Item
 - The code of the BOM item linked to the supply order.
 - Supply Order Transaction
 - The transaction number of the supply order.
 - Sourcing Process
 - The code of the sourcing process. A process to supply an item by manufacturing, distribution, or purchasing.
 - Sourcing Process
 - The code of the sourcing process. A process to supply an item by manufacturing, distribution, or purchasing.
 - SO Step Supplying
 - The code of the supply order step.
 - SO Step Supplying
 - The code of the supply order step.
 - Split Element
 - The code of the split element.
 - SO New RCM
 - The supply order number of the new recommendation.