Recommendation (plaps6601m000)

Use this session to view and maintain the action suggested by the Requirements engine to improve the production plan.

Field Information

Scenario
The code of the scenario.
Recommendation
The unique identification code of the recommendation.
Plan Item
The code of plan item. The code consists of the cluster code, the project code, and the item code.
Types

The type of recommendation.

Allowed values

SO New RCM
Substitution Supply RCM
Skip Supply RCM
Use Target Inventory RCM
Postpone RCM
Expedite RCM
Decrease RCM
Cancel RCM
Split RCM
RCM Date
The date and time when the recommendation is made.
RCM Quantity
The quantity recommended.
Status

The status of the recommendation.

Allowed values

New
Automatically Accepted
Accepted
Rejected
Action

The recommended action.

Allowed values

Postpone
Expedite
Decrease
Cancel
SO New
Substitution Supply
Use Target Inventory RCM
Skip Supply
RCM Finish Date
The recommended finish date.
Transaction Code
The code of the transaction.
Modify Quantity
Modify Duration
The quantity modified.
Initial Date
The original due date of a supply order for which the Requirements engine has recommended a change of date.
RCM Finish Date
The recommended finish date.
Deleted Supply Order
The code of supply order that is deleted.
Original Supply Order
The actual supply order which is created.
Initial Quantity
The total quantity which is planned initially.
Planned Supply Order
The code of the planned supply order.
Supply Order
The code of the supply order.
Sourcing Process
The code of sourcing process. A process to supply an item by manufacturing, distribution, or purchasing.
Substitute Plan Item
The plan item that acts as a substitute.