Resource Utilization Options (plaps0181m000)
Use this session to view and maintain the settings of the Resource Utilization graph.
Field Information
- Username
- The logon code of the user who modifies the Resource Utilization settings.
- General
-
- Scenario
- The code of the scenario.
- Horizon
-
- Horizon Type
-
The time period which the data to be displayed in the Resource Utilization graph.
Allowed values
- Absolute
- Relative
- Absolute
-
- Start Date
-
The start date of the horizon.
Note: This field is enabled only if the Horizon Type field is set to Absolute.
- End Date
-
The end date of the horizon.
Note: This field is enabled only if the Horizon Type field is set to Absolute.
- Relative
-
- Quantity
-
The time period and units to consider while displaying the data in the Resource Utilization graph.
Note: This field is enabled only if the Horizon Type field is set to Relative.
- Units
-
The units in which the horizon is expressed.
Allowed values
- Days
- Weeks
- Months
- Years
- Filters
-
- Resource
-
The filters applied on a series of the graph based on the resource capacity use.
Allowed values
- No Filter
- All resources are displayed.
- With Utilization
- The resources with projected capacity are displayed.
- With Overload Period
- The resources with at least one period of overload are displayed.
- With Average Utilization Overloaded
- The resources whose capacity is overloaded on average are displayed.
- With Utilization without Capacity
- The resources with jobs scheduled when capacity is not available are displayed.
- Type
-
The resource type to be displayed in the Resource Utilization graph.
Allowed values
- Constrained Type
- Unconstrained Type
Note: You can select the Constrained Type and Unconstrained Type resources at a time.
- Threshold
-
The point at which a resource is considered overloaded.
Note: You must specify the value in percentage.
- Capacity
-
The capacity mode to be displayed in the Resource Utilization graph.
Allowed values
- Infinite
- Finite
- Chart
-
- Automatic Horizon
-
If this check box is selected, a limited number of buckets within the plotting area are displayed in the Resource Utilization graph.
Note: By default, this check box is selected.
- Calendar
-
- Effective Availability
- If this check box is selected, the availability of resources based on the calendar are displayed in the Resource Utilization graph.
- Aggregation
-
This field consolidates the resource utilization percentages into a single series, averaged based on the selected type.
Allowed values
- All
- Selected
- Same Site
- Same Resource Group
- None
- Detailed
-
- View Type
-
The view type to be displayed in the Resource Utilization graph.
Allowed values
- Setup vs Production
- The detailed view displays the proportion of capacity used for setup time versus production time within each time bucket for the requested horizon.
- Lateness Type
- The detailed view displays the proportion of capacity allocated to producing early, on-time, and late orders within each time bucket for the requested horizon.
- Order Status
- The detailed view displays the proportion of capacity allocated to producing planned, firm planned, and released orders within each time bucket for the requested horizon.
- Allocation Type
- The detailed view displays the resources based on the allocation type.
- View Mode
-
The type of the resource utilization display.
Allowed values
- Hours
- Percentage
- Buffer Information
-
This field determines whether to add or remove a series from the graph that displays the buffer information of the resources.
Allowed values
- Time
- The average buffer time of all operations that are planned to start on that day are displayed.
- Average Work buffer
-
The number of extra hours of work available for a resource at a specific time is displayed.
Note: This option is available only when the graph is grouped by day.
- None
- The buffer information is not displayed in the graph, except for the Planning Buffer.
- Lateness Variation
-
- Early Orders
- The color code for indicating early orders in the Resource Utilization graph.
- On Time Orders
- The color code for indicating on time orders in the Resource Utilization graph.
- Late Orders
- The color code for indicating late orders in the Resource Utilization graph.
- Tolerance
-
- Threshold
-
The lateness tolerance threshold for the Resource Utilization graph.
Note: The orders turn to white if they are less late. This is based on the value specified in this field.
- Granularity
- The granularity color that indicates how late or early an order is based on the color saturation (how close or far it is from white).
- Color
-
- Planned Orders
- The color code for indicating planned orders in the Resource Utilization graph.
- Firm Planned Orders
- The color code for indicating firm planned orders in the Resource Utilization graph.
- Released Orders
- The color code for indicating released orders in the Resource Utilization graph.
- Confirmed Orders
- The color code for indicating confirmed orders in the Resource Utilization graph.
- Setup Time
- The color code for indicating setup time for resources in the Resource Utilization graph.
- Production
- The color code for indicating production of the resources in the Resource Utilization graph.
- Customer Order Allocations
- The color code for indicating customer order allocations in the Resource Utilization graph.
- Warehouse Demand Orders
- The color code for indicating warehouse demand orders in the Resource Utilization graph.
- Other Order Allocations
- The color code for indicating other order allocations in the Resource Utilization graph.
- Capacity
-
- Available
- The color code for indicating available capacity of resources in the Resource Utilization graph.
- Used
- The color code for indicating used capacity of resources in the Resource Utilization graph.
- Overload
-
- Duration
- The color code for indicating overload duration of resources in the Resource Utilization graph.
- Maximum
- The color code for indicating maximum overload of resources in the Resource Utilization graph.
- Average
- The color code for indicating average overload of resources in the Resource Utilization graph.