Check-out related drawing files
          When user performs check-out operation on a drawing file, the integration will check-out its related model. Also, if check-out operation is performed on a model, the integration will check-out its related drawings.
         
         To enable this functionality, PLM Administrator needs to set the Projects’ Vault Parameter.


          Note: Limitations
          
        - Drawing must contain views of only one Model. But, if the drawing contains views of multiple models, then the check-out operation from one Model will not impact the other Models.
 - The integration user can check-out only the latest revision of the document. If a user wants to check-out previous revisions of any document, that can be done from the PLM. In this case the user must perform the Edit File after performing the check-out from the PLM.