Product BOM (pdpdm1651m000)
Use this session to view the product item.
These sessions are displayed as satellite sessions:
- Local Alternative Product Items (pdpdm1153m000)
 - Product Reference Designators (pdpdm1152m000)
 
Field Information
- Site
 - The site (location) to which the item belongs.
 - Parent Item
 - 
            
The code of the parent item.
Note: This value is defaulted from the PLM Items (pdpdm1500m000) session. - Revision
 - The revision number of the parent item.
 - Description
 - The description or name of the code.
 - Find No.
 - The number that enables you to compare the Item attributes and the attributes of the linked properties.
 - Component
 - The code of the component.
 - Status
 - 
            
The status of the Item.
Allowed values
- Draft
 - Released
 - Under Change
 - Obsolete
 
 - Status
 - 
            
The status of the parent Item.
Allowed values
- Draft
 - Released
 - Under Change
 - Obsolete
 
 - Status
 - 
            
The status of the child Item.
Allowed values
- Draft
 - Released
 - Under Change
 - Obsolete
 
 - Life Cycle
 - 
            
The stage at which the Item is, in the production life cycle. This is used to track the Item through the various phases (from design to production).
Allowed values
- In Design
 - Approved to Production
 - Released to Production
 
 - Life Cycle
 - 
            
The name used to track the child Item through its various stages; from design the production.
Allowed values
- In Design
 - Approved to Production
 - Released to Production
 
 - Bill of Material
 - The code of the bill of material (BOM).
 - BOM Status
 - 
            
The status of the Item.
Allowed values
- Draft
 - Approved
 
 - Quantity
 - 
            
- Net Quantity
 - The goods quantity on the order, expressed in the inventory unit.
 - Scrap Quantity
 - The item quantity that is considered as scrap.
 - Scrap Percentage
 - The percentage of the item value that is considered as scrap.
 - Unit of Measure
 - The unit of measure used for the item.
 - BOM Unit
 - The BOM Unit to be defined at the component level.
 - Length
 - The length of the item.
 - Width
 - The width of the item.
 - Size Unit
 - The unit of measurement for the Length and Width fields.
 - Number of Units
 - The number of units of the item.
 - Skip to Production
 - 
              
If this check box is selected, the item skips to production.
 - BOM Line Text
 - The additional information required for the task.
 
 - Use Up
 - 
            
- Replaces Item
 - The material from the previous BOM revision, which is now a use-up material. As long as the use-up material is present in inventory, it will be used instead of the material specified in the item field.
 
 - Miscellaneous
 - 
            
- Standard Configuration
 - If this check box is selected, the item is produced with a standard configuration.
 - Phantom
 - If this check box is selected, the item is a phantom item.
 - Warehouse
 - The default warehouse in which the item is stored.
 - Operation
 - The action to be performed on the selected field or column.
 - Alternatives Present
 - Indicates if alternative item are available for the BOM lines.
 - Reference Designators Present
 - Indicates if reference designator is available for the BOM lines.
 - Text
 - Indicates if the BOM text is defined for the BOM line.
 
 - CAD Instance Name
 - The name of the variant in the CAD family.
 - Compliance Status
 - 
            
The item's compliance according to RoHS directive.
Allowed values
- No Data
 - Pass
 - Pass with Exemptions
 - Fail
 - Conditional Fail
 - Partial Fail
 - Not Relevant
 - Not Applicable
 
 - Link Effective From
 - The date from which the effectivity of the BOM is applicable.
 - Link Effective To
 - The date up to which the local alternate product item is effective. The application sets the date when a new revision of the item is released.
 - Originating App
 - The application using which the BOM is created.
 - Approval Date
 - The date on which the BOM is released.
 - Security Access Level
 - 
            
The level of security access provided to the user.
Allowed values
- Unrestricted
 - Restricted
 - Confidential
 - Secret
 - Top Secret
 
 - Created By
 - The name of the user who creates the BOM.
 - Item Type
 - 
            
The item type used for the project.
Allowed values
- Purchased
 - Engineering Module
 - Manufactured
 - Product
 - Generic
 
 - Created On
 - The date and time when BOM is created.
 - Previous Revision
 - The alpha numeric code of the existing revision of the Item.
 - Derived From
 - The original item from which this item is copied.
 - The original item revision from which this file is derived.
 - Category
 - The code of the item category.
 - The name of the item category.
 - Business Process
 - The business process for which the item is required.
 - Modification
 - The code of the modification.
 - Standard
 - The standard of the item.
 - Serialized
 - If this check box is selected, the item is serialized.
 - Lot Control
 - If this check box is selected, the item is lot controlled.
 - End Item
 - If this check box is selected, the item is an End item.
 - Cost
 - The cost of the item.
 - Currency
 - The currency in which the item cost is specified.
 - Obsolete
 - Indicates that the item is no longer in use.
 - Estimated Weight
 - The estimated weight of the manufactured item.
 - Customizable
 - 
            
Indicates if the item is customized.
Allowed values
- make-to-order
 - anonymous item
 
 - Size
 - The default size of the item.
 - Material
 - The material from which the item is manufactured.
 - Object Type
 - 
            
The category of the object.
Allowed values
- Item
 - Folder
 - Maintenance Sales Order
 - Maintenance Sales Order Item Lines
 - Bill of Material
 - Contracts
 - Inspection Plans
 - Inspection Plan Characteristics
 - Serial End Item Header
 - Serial End Item Components
 - Opportunity
 - Warehouse Order
 - Business Process
 - Planned Order
 - Purchase Requisition Order
 - Incident Number CAR
 - Incident Number CAR1
 - Incident Number CAR2
 - Incident Number CAR3
 - CUSAI Number
 - Planned Item
 - ERP Work Center
 - Instruments
 - Tool
 - Installation
 - Adjustment Order
 - Adjustment Order Line
 - Warehouse Receipt
 - Match Approve Pur Inv
 - Manufacturer
 - Supplier
 - Contractor
 - Category
 - File
 - Hardcopy
 - Business Process Comment
 - ECM File
 - ECM Document
 - Purchase Order
 - Purchase Order Line
 - Sales Order
 - Sales Order Line
 - Production Order
 - Service Order
 - Routing
 - Routing Line
 - Fixed Asset
 - Sales Quotation
 - Sales Quotation Line
 - Purchase Inquiry
 - Purchase Inquiry Line
 - ECM Project
 - Charge Element
 - Employee
 - Business Partner
 - Customer Business Partner
 - Supplier Business Partner
 - LOT
 - Abstract Items
 - Configuration Items
 - Service Order Activity
 - Project (TP)
 - Project (PCS)
 - E Item
 - P Item
 - Service Installation
 - Installation Component
 - Customize Routing
 - Customize Routing Line
 - ERP Task
 - Generic
 - ERP Machine
 - Customized Item
 - Service Call
 - Service Contract
 - Service Contract Quote
 - Service Order Quote
 - Service Quote Activity
 - Reference Activity
 - ECO
 - Budget
 - Feature
 - Calculation Part
 - Routing Sheet Budget
 - Routing Sheet Operation
 - Sales Activity
 - Purchase Requisition
 - Purchase Req Line
 - SCH Sales Contract
 - SCH Sales Contract Line
 - SCH Purchase Contract
 - SCH Purchase Cont Line
 - Option
 - NCR
 - Abstract File
 - Abstract Document
 - Abstract BP
 - Illustration
 - Material
 - Formula
 - Markup
 - Tessellation
 - Plan Material Purchase Order
 - Project Activity
 - Labor Budget
 - Equipment Budget
 - Subcont Budget
 - Sundry Budget
 - Purchase Advice
 - Purchase Advice Line
 - Material Requisition
 - Work Breakdown Structure
 - System
 - Document
 - System Part
 - Space
 - Received Invoices
 - Received Pur Invoices
 - Received Pur Inv Line
 - Serialized Items
 - Serial Numbers
 - Physical Breakdowns
 - Work Order
 - Work Order Activities
 
 - Activity/Element
 - The default code of the project element / activity linked to the item.
 - Long Lead Item
 - If this check box is selected, the item is the long lead item.