Examples of subcontracting rates

The following data is used in the examples:

Subcontracting rate $50
Subcontracting factor 1.0
Gross output 170
Labor hours run Gross output * cycle time (hrs) = 170 * 0.1 = 17
Machine hours run Gross output * cycle time (hrs) = 170 * 0.1 = 17
Labor hours setup Setup time (hrs) = 2
Machine hours setup Setup time (hrs) = 2

Unit

Subcontracting costs = gross output * subcontracting rate = 170 * 50 = $8,500.

Hour

Subcontracting costs = (machine hour setup + machine hours run) * subcontracting rate = (2 + 17) * 50 = $950.