Resource Capacity (Machine Capacity) (cprpd2102m100)
Use this session to display machine capacity group capacity details. The graph shows the capacity of the calendar working hours per week, up to eight weeks.
Field Information
-
- Resource
-
The resource ID.
- Resource Type
-
The type of resource.
- Capacity Type
-
The type of capacity that applies to the resource.
Allowed values
- Labor
- Machine
- Item
- Capacity Type Unit
-
The unit type in which capacity is defined.
Allowed values
- Hours
- Days
- Capacity Type Bucket
-
The length of a capacity bucket: one week.
-
- Machine Type
-
The machine type that is part of the resource.
- Work Center
-
The work center that is part of the resource.
- Production Department
-
The production department that is part of the resource.
- Production Site
-
The site that is part of the resource.
- Planning Cluster
-
The cluster the resource to which the resource belongs.
-
- Critical
-
If this check box is selected, the selected capacity is critical to planning.
- Available Machines
-
The number of machine available to the selected resource.
- Actual Calendar
-
The actual calendar used by the selected resource.
- Origin
-
The source of the calendar.
-
- <
-
The button to move the graph to the left.
- >
-
The button to move the graph to the right.