Printing Critical Material Requirements
LN prints a report about the critical material requirements as displayed in the Critical Material Requirements (cprmp2505m000) session.
To print a report of critical material requirements:
- 
            
Select a range of:
- Scenarios
 - Plan periods, in which the planned supply of the end items falls.
 - Plan items (end items)
 - Periods in which the components are required.
 - Required plan items (components)
 
 - Click
 - Select a report type in the Select Report list box and click OK.
 
You can select the following two types of reports:
- 
            
Critical Material Requirements by Plan Item
LN prints a report that lists all the critical material requirements that originate from a specific plan item. - 
            
Critical Material Requirements by Component
LN prints a report that lists the items for which a particular required item, or a range of required items, forms a critical material requirement.