General lead times
The following table lists the lead time components, the calendar, and availability type that are used to plan the general lead times.
| Lead time component | Sequence to find calendar: | 
|---|---|
| Safety time (BP) | 
              
  | 
            
| Safety time (item) | 
              
  | 
            
| Extra lead time | 
              
  | 
            
| Inbound lead-time | 
              
  | 
            
| Outbound lead-time | 
              
  | 
            
Safety time and extra lead time use the calendar linked to the plan item. The calendar is retrieved as follows:
- Enterprise unit of plan item in the Items - Planning (cprpd1100m000) session
 - Company calendar in the Companies (tcemm1170m000) session
 
Warehouse inbound and outbound times are linked to the (item-) warehouse data of the planned order. The warehouse calendar is used to calculate inbound and outbound times.