下达服务订单 (tssoc2200m000)
仅当在服务订单页眉中选择了“准备下达”选项后,才能使用此进程以下达一组或一批“自由”或“已计划”状态的服务订单。此复选框的默认选项为“是”。必须为某个活动分配一个或多个工程师,或者为要下达的服务订单分配一个页眉工程师。
仅当在服务订单 (tssoc2100m000) 进程中未选择任何记录时,进程中才会显示范围字段。
- 服务部门
-
“自”和“至”字段可定义以下一组内容: service departmentsfor which the service orders must be released.
- 服务区域
-
“自”和“至”字段可定义以下一组内容: service areas for which the service orders must be released.
- 服务订单
-
“自”和“至”字段可定义以下一组内容: service orders which must be released.
- 买方业务伙伴
-
“自”和“至”字段可定义以下一组内容: Sold-to Business Partners for whom the service orders must be released.
- 首选工程师
-
“自”和“至”字段可定义以下一组内容: service engineer for whom the service orders must be released.
- 项目
-
“自”和“至”字段可定义以下一组内容: projects for which the service orders must be released.
- 服务合同
-
“自”和“至”字段可定义以下一组内容: service contracts for which the service orders must be released.
- 计划起始时间
-
The range of the date and time on which the execution of service order is planned to begin.
- 计划结束时间
-
The range of date and time on which the execution of service order is planned to finish.
- 最早起始时间
-
The range of the earliest start date and time for the execution of the service orders.
- 最晚结束时间
-
The range of the latest finish date and time for the execution of the service orders.
- 复制估计值至实际值 (其它成本)
-
如果选中此复选框, the estimated costs are copied to the actual costs when the service order is released.
- Check Capacity Availability
-
如果选中此复选框, the order duration is checked. The order duration must be less than or equal to the available hours between the Planned Start time and Planned Finished time.如果清除此复选框, the order duration is not checked.
- Check Skill status
-
如果选中此复选框, the skill set of the assigned engineer for each service order selected is checked against the skills required to perform the activity. The sequence and priority of the skills are mentioned in 通用服务参数 (tsmdm0100m000)session. This check however, is not hard commited.如果清除此复选框,the skill set is not checked and the service orders are released.
- 检查任务分派
-
Indicates if assignments are linked to all the activities.
默认值
By default, this check box is selected.
Note:This check box is visible only if the 任务分派是必需的 check box is not selected in the 服务订单管理参数 (tssoc0100m000) session.
- Check Project Status
-
如果选中此复选框, the project status of the service order is checked. The project status must be Active for the service order to be released. This option is only applicable if the service order is linked to ERP Projects. You can manually link a project to a service order or a service order quotation.如果清除此复选框, the Project Status is not checked and the service orders are released.
- Check Inventory Availability
-
如果选中此复选框, the availability of inventory for the material requirement line is checked. If the inventory is insufficient, an error message appears and user can choose to continue with the releasing of the service order. This check however, is not hard commited.如果清除此复选框,the availability of material requirement lines are not checked and the service order is released.
- Check Service Kit Allocation
-
如果选中此复选框,the service kit allocated for a material requirement line is checked. If the service kit cannot be allocated for the execution of the service order, then the Release action is terminated. To proceed with the releasing of service orders, irrespective whether the material requirement lines are met, you can delete the unprocessed estimated lines.如果清除此复选框,the availability of service kits are not checked and the service order is released.
- 下达状态为“自由”的订单
-
如果选中此复选框, the order with status set to 'Free' and 'Planned' can be released. 如果清除此复选框, only order with status set to 'Planned' can be released.
Note:By default, this check box is selected.
- 材料可用性
-
- 检查 ATP 库存
-
如果选中此复选框, the ATP Inventory check is performed.
Note:The ATP check is only performed, if the 订货系统 is set to 计划订货系统 in the 物料 (tcibd0501m000) session and the 包括在企业计划中 check box is selected in the 仓库 (tcmcs0103s000) session.
- 跳过冻结库存
-
如果选中此复选框, the blocked quantity is subtracted from the On Hand quantity during the Planned Inventory check and the On Hand Inventory check.
Note:This field is enabled only if the 检查计划库存 check box or the 检查现有库存 check box is selected.
- 检查计划库存
-
如果选中此复选框, the Planned Inventory check is performed.
- 检查现有库存
-
如果选中此复选框, the On Hand Inventory check is performed.
- 库存检查范围
-
Check if the material is available in the warehouse defined on the Material Line (Current Warehouse Only) or in one of the warehouses in the same cluster as the warehouse defined on the Material Line (All Warehouses in Cluster).
Note:This field is enabled only if the 检查计划库存 or the 检查现有库存 check box is selected.
允许值
- 计划群中的所有仓库
-
检查在材料行上定义的仓库中的材料是否可用。
- 仅限当前仓库
-
检查与材料行上定义的仓库相同的群中的其中一个仓库中的材料是否可用。
- 短缺时间计划
-
- 更新材料行的计划交货时间
-
如果选中此复选框, the Planned Delivery Time of the Material Lines is updated with the Planned Available Date when 库存检查状态 is set to 供应延误 or 短缺 in the 服务材料可用性 (tstdm2520m000) session. When this check box is selected, the performed inventory check (ATP Inventory or Planned Inventory) is recalculated after the update.
Note:This field is enabled only if 检查 ATP 库存 or 检查计划库存 is selected.
- 使用最新的计划材料行更新活动和订单
-
如果选中此复选框, the Planned Start time of the orders and the activities of the related material line, are updated with the latest Planned Delivery time of the material lines..
- 将材料与最新的计划材料行同步
-
如果选中此复选框, the Planned Delivery time of all material lines belonging to the order or activity are updated with the last Planned Delivery time of the material lines.
- 处理报告
-
/baanerp/ts/onlinemanual/000071
- 错误报告
-
/baanerp/ts/onlinemanual/000070
- 信息报告
-
如果选中此复选框, LN displays the error or information message, which are defined in the Infor LN 仓储.
When you release a service order, warehouse orders get generated in the Infor LN 仓储. Warehouse orders can be automatically processed. When warehouse orders are processed, LN throws errors or displays messages related to processed warehouse orders. These messages are displayed in the information report.