活动预算(杂项成本)(tpptc2114m000)

使用此进程以为选定的活动、计划和项目维护成本类型杂项成本的预算行。

项目

The code that uniquely identifies the project.

说明

代码的说明或名称。

Status

The project status.

允许值

自由
活动
已结束
已结
已存档
计划

The code that uniquely identifies the plan .

Activity

The code that uniquely identifies the activity.

Description

代码的说明或名称。

Activity Status

The budget status of the activity.

允许值

自由

您可以修改所有数据。

实际

您可以修改预算数据并生成控制数据。 还可以记录预算历史记录。

最终

您不可修改预算数据。 只能通过预算调整来添加或更改预算行。 还可以记录实际预算历史记录。 .

预算日期

The budget date that is used as the reference for currency transactions. By default, the budget date as specified for the project is added to the new budget lines.

行号

The code that uniquely identifies the line number.

Line Number

An asterisk indicates that the budget line belongs to an adjustment.

杂项成本

The code that uniquely identifies the sundry costs code.

Description

代码的说明或名称。

Sundry Cost

The nature of the sundry costs cost object.

预算调整

如果选中此复选框, the budget line belongs to an adjustment.

Note: 

If adjustment is specified for a budget line, the adjustment code is displayed along with the difference amount in the 附加信息 group box.

通用
预算明细
数量

The quantity of the sundry cost.

Note: 

The default net quantity is given according to the following calculation: adjustment balance amount = unit cost x net quantity So if the adjustment balance amount is 100 and the unit cost is 10, the default net quantity will be -10. The calculated default net quantity is usually a negative value, because then the adjustment balance results in a balance of zero.

Unit

The code that uniquely identifies the unit of measure.

预算状态

The budget-line status.

允许值

自由

您可以修改所有数据。

实际

您可以修改预算数据并生成控制数据。 还可以记录预算历史记录。

最终

您不可修改预算数据。 只能通过预算调整来添加或更改预算行。 还可以记录实际预算历史记录。 .

文本

如果选中此复选框,将显示文本。

相关详细资料
成本构成

The code that uniquely identifies the cost component linked to the sundry cost.

Note: 

You can only specify a cost component for which the 构成类型 is set to 明细 or 综合 in the 成本构成 (tcmcs0148m000) session.

Description

代码的说明或名称。

延伸合同

The code that uniquely identifies the extension.

Description

代码的说明或名称。

相关起始日期

The start date related to the project plan.

相关结束日期

The finish date relative to the project plan.

成本详细资料
单位成本

The standard cost per unit cost item.

Unit Cost Currency

The currency to express the unit cost of the item.

最终单位成本

如果选中此复选框, the cost rate of the activity budget line is final and the corresponding budget lines for the project is updated with the same cost rate.

Note: 

If this check box is cleared, the cost rate for the activity budget line can be modified .

成本金额

The cost amount of the sundry cost item.

Cost Amount

The text that indicates if the cost amount is a purchase price.

Currency Rate

The currency rate.

Rate Factor

The currency rate factor.

意外准备金

The provisional amount that includes the possible unexpected costs.

Currency

The value is defaulted from the currency in which the 成本金额 is specified.

本币金额

The cost amount in the home currency.

Home Currency

The home currency for the cost amount.

销售详细资料
销售价格

The sales price of the sundry cost item.

Sales Price Currency

The business partner currency.

销售金额

The sales amount of the budget line.

Home Amount

The sales amount in the home currency.

Home Currency

The home currency for the sales amount.

Currency Rate

The currency rate.

Rate Factor

The currency rate factor.

附加信息
Adjustment Code

The adjustment code.

These fields are also displayed, if adjustment is specified for the budget line.

  • Difference amount: The difference amount based on the budget adjustment.
  • Currency: The currency in which the difference amount is expressed.
  • Quantity: The quantity specified for the activity. This value is defaulted from the 数量 field in the 活动 (tppss2100m000) session.
  • Amount of time: The time unit specified for the activity. This value is defaulted from the 时间单位数 field in the 活动 (tppss2100m000) session.
集成
外部进度计划编制子系统
日历

The code that uniquely identifies the calendar linked to the activity budget.

持续时间

The duration of the activity budget.

持续时间单位

The time unit in which the duration of the activity budget is expressed.

服务
服务相关

如果选中此复选框, the item is linked to a service order.

已转移至服务管理子系统

如果选中此复选框, the item is transferred to 服务管理子系统 as a service order.