活动预算(设备)(tpptc2112m000)
- 项目
-
The code that uniquely identifies the project.
- Description
-
代码的说明或名称。
- Status
-
The project status.
- 计划
-
The code that uniquely identifies the plan.
- Activity
-
The code that uniquely identifies the activity.
- Description
-
代码的说明或名称。
- Activity Status
-
The budget status of the activity.
允许值
- 自由
-
您可以修改所有数据。
- 实际
-
您可以修改预算数据并生成控制数据。 还可以记录预算历史记录。
- 最终
-
您不可修改预算数据。 只能通过预算调整来添加或更改预算行。 还可以记录实际预算历史记录。 .
- 预算日期
-
The budget date that is used as the reference for currency transactions. By default, the budget date as specified for the project is added to the new budget lines.
- 卖方业务伙伴
-
The buy-from business partner.
- 行号
-
The code that uniquely identifies the line number.
- Line Number
-
An asterisk indicates that the budget line belongs to an adjustment.
- 设备
-
The code that uniquely identifies the equipment.
- Description
-
代码的说明或名称。
- Equipment
-
The nature of the equipment cost object.
允许值
- 项目
-
特定于选定的项目。
- 标准
-
通用于所有项目。
- 预算调整
-
如果选中此复选框, the budget line belongs to an adjustment.
Note:If adjustment is specified for a budget line, the adjustment code is displayed along with the difference amount in the 附加信息 group box.
- 通用
-
- 预算详细资料
-
- 时间量
-
The amount of time that the equipment is used.
- Amount of Time Unit
-
The code that uniquely identifies the time unit.
- 外部
-
如果选中此复选框, the equipment cost object is external. An external equipment is rented externally from a business partner while an internal equipment is expected to be provided by an internal equipment department.
- 预算状态
-
The status of the budget line.
允许值
- 自由
-
您可以修改所有数据。
- 实际
-
您可以修改预算数据并生成控制数据。 还可以记录预算历史记录。
- 最终
-
您不可修改预算数据。 只能通过预算调整来添加或更改预算行。 还可以记录实际预算历史记录。 .
- 文本
-
如果选中此复选框,将显示文本。.
- 相关详细资料
-
- 成本构成
-
The code that uniquely identifies the cost component linked to the equipment.
Note:You can only specify a cost component for which the 构成类型 is set to 明细 or 综合 in the 成本构成 (tcmcs0148m000) session.
- Description
-
代码的说明或名称。
- 延伸合同
-
The code that uniquely identifies the extension.
- Description
-
代码的说明或名称。
- 相关起始日期
-
The start date related to the project plan and concerned with the budget. This date changes automatically when the scheduled start date of the activity (in the 活动 (tppss2100m000) session) is changed.
- 相关结束日期
-
The finish date relative to the project plan.
- 成本详细资料
-
- 成本费率
-
The cost rate of the equipment cost object.
- Cost Rate Currency
-
The currency for the cost amount.
- 最终成本费率
-
如果选中此复选框, the cost rate of the activity budget line is final and the corresponding budget lines for the project is updated with the same cost rate.
Note:If this check box is cleared, the cost rate for the activity budget line can be modified.
- 意外准备金
-
The provisional amount that includes the possible unexpected costs.
- 币种
-
The value is defaulted from the currency in which the 成本金额 is specified.
- 到岸成本分类
-
The landed costs classification code for the activity budget of the equipment.
- Description
-
代码的说明或名称。
- 到岸成本金额
-
The landed cost amount for the activity budget of the equipment.
- 成本金额
-
The cost amount for the equipment.
- Cost Amount
-
The text that indicates if the cost amount is a purchase rate.
- Currency Rate
-
The currency rate.
- Rate Factor
-
The currency rate factor.
- 本币金额
-
The cost amount in the home currency.
- Home Currency
-
The home currency for the cost amount.
- 销售详细资料
-
- 销售费率
-
The sales rate.
- Sales Rate Currency
-
The business partner currency.
- 销售金额
-
The total sales amount of the budget line.
- Home Amount
-
The sales amount in the home currency.
- Home Currency
-
The home currency for the sales amount.
- Currency Rate
-
The currency rate.
- Rate Factor
-
The currency rate factor.
- 附加信息
-
- Adjustment Code
-
The adjustment code.
These fields are also displayed, if adjustment is specified for the budget line.
- Difference amount: The difference amount based on the budget adjustment.
- Currency: The currency in which the difference amount is expressed.
- Quantity: The quantity specified for the activity. This value is defaulted from the 数量 field in the 活动 (tppss2100m000) session.
- Amount of time: The time unit specified for the activity. This value is defaulted from the 时间单位数 field in the 活动 (tppss2100m000) session.
- 集成
-
- 外部进度计划编制子系统
-
- 日历
-
The code that uniquely identifies the calendar linked to the activity budget.
- 持续时间
-
The duration of the activity budget.
- 持续时间单位
-
The time unit in which the duration of the activity budget is expressed.
- 服务
-
- 服务相关
-
如果选中此复选框, the item is linked to a service order.
- 已转移至服务管理子系统
-
如果选中此复选框, the item is transferred to 服务管理子系统 as a service order.