按项目列出的活动概览 (tipcs4502m000)

使用此进程以显示按项目列出的活动列表。

项目

A collection of manufacturing and purchasing actions that are performed for a particular customer order. A project is initiated to plan and coordinate the production of the to be manufactured items.

For a standard-to-order production, the project is only used to link the item with the customer order. A project can also include these:

  • Customized item data (BOMs and routings)
  • Project planning (activity planning)
项目状态

Indicates the current progress of the project.

活动

This code identifies an activity in the network planning for a project.

搜索关键字

为便于搜索而使用的另一种形式的说明。它通常是完整说明的缩写、首字母缩写或便于记忆的替代说明。

任务

LN shows the number of the task linked to the activity.

The task number gives more detailed information about the activity.

工作中心

The code of the work center or the main work center where the activity is carried out.

活动管理员

A person responsible for planning or carrying out a project activity.

文本

This field shows whether or not a text is present.

能力负荷表

A table in which you can define how the rough capacity requirements are to be distributed over the capacity duration. The x coordinate is a percentage of the activity duration. The y coordinate is a percentage of rough capacity requirements.

粗略能力

The globally needed capacity in hours for the execution of the relevant activity.

汇总能力

The aggregated capacity requirements in hours of the work center where the activity is scheduled to be carried out. The aggregated capacity requirements are calculated in the 汇总项目估计能力 (tipcs4201m000) session on the basis of the project structure and the project engineering. You can only do this if the operations have been linked to activities in the customized routing. Dependent on the value of the 在资源主计划中显示 field in the 工作中心 (tirou0101m000) session, 人工能力 or 机器能力 is used to calculate the aggregated capacity.

The aggregated capacity requirements are only shown for your information and can be used for checking or monitoring the rough planned hours by activity.

平均能力

Enter the available capacity in hours per day. This capacity is used to calculate the default activity duration. The planning factor enables you to record the available capacity in hours per day for each employee or machine.

Based on this capacity, LN calculates the default duration of an activity using the appropriate formula:

Default activity duration = Rough capacity requirement / (Planning factor x Available Capacity)

计划因子

The planning factor indicates how many employees or machines are employed simultaneously for the execution of an activity. This factor is used only to calculate the default duration of the activity on the basis of the global capacity requirements and the available hours per day.

提前期

The time between the production start date and the delivery date. The lead time can include order preparation time, transportation time, and inspection time.

最早起始日期

The earliest date on which the activity can be started. You can determine this date using the 生成网络计划 (tipcs4210m000) session.

最晚起始日期

The last date on which the activity can be started. Determine this date by using the 生成网络计划 (tipcs4210m000) session.

最早终止日期

Rhe earliest date on which the activity can be completed. Determine this date using the 生成网络计划 (tipcs4210m000) session.

最迟终止日期

The last date on which the activity can be completed. Determine this day using the 生成网络计划 (tipcs4210m000) session.

合计浮动时间

The total float of an activity is the maximum time expressed in (working) days in which that activity can be shifted without affecting the planned completion date of the relevant project.

The total float-time is calculated as follows:

Total Float = Latest Finish - Earliest Start - Activity Duration

The latest finish date and earliest start date are expressed in project days.

Note: 

The corresponding Total Slack field in MS Project is expressed in hours.

The conversion is based on the 工作中心 field and the 按资源单位列出的日基本能力 field linked to the specified work center.

自由浮动时间

The free float time between one activity and the next. The free float time indicates how many days the activity can be extended without jeopardizing the progress of other related activities.

Note: 

The corresponding Free Slack field in MS Project is expressed in hours.

The conversion is based on the 工作中心 field and the 按资源单位列出的日基本能力 field linked to the specified work center.

要求起始日期

The date on which you want to start the relevant activity. This date is only used for information. However, the desired start date is compared to the earliest and latest finish dates and the reference date in the 生成网络信息 (tipcs4211m000) session. This can result in the creation of exception messages.

要求结束日期

The date on which you want to stop the execution of the relevant activity. This date is only used for information. However, the desired finish date is compared to the earliest and latest finish date and the reference date via the session 生成网络信息 (tipcs4211m000), which can result in the creation of exception messages.

参与估算

Indicates whether the relevant activity must be included in the estimated cost-price calculation for the project. This can be especially important for indirect activities, such as engineering.

低层代码

The Low Level code indicates the lowest level at which the activity is found in the activity network for the project. This code is determined by the 生成网络计划 (tipcs4210m000) session.

实际起始日期

The actual start date for the activity is the date on which its execution was started. LN fills the actual start date, when transaction hours are processed with the 处理工时和费用 (bptmm1203m000) session, or when a network calculation is executed using the 生成网络计划 (tipcs4210m000) session. You can change this date manually.

实际终止日期

The actual finish date for the activity is the date on which time was last spent on or on which the activity was completed. LN fills the actual finish date, when transaction hours are processed with the 处理工时和费用 (bptmm1203m000) session, or when a network calculation is executed using the 生成网络计划 (tipcs4210m000) session. You can change this date manually.

耗用关键能力

The actual hours spent on the relevant activity. Based on the hours transactions linked to the activity, LN automatically updates this value in the 处理工时和费用 (bptmm1203m000) session.

完成百分比

The percentage completed shows the activity's progress.

Note: 

Because of the non-linear distribution of capacity-requirements, the percentage completed is not related to the lead-time but to the global capacity-requirements. If you choose an automatic calculation of the percentage completed, this percentage is determined on the basis of the global capacity-requirements and the actual hours spent.

自动更新

This field indicates whether the percentage completed must be automatically determined using either the 处理工时和费用 (bptmm1203m000) session when transaction hours are processed, or the 生成网络计划 (tipcs4210m000) session when a network calculation is executed for the project.