生成产品变型的(项目)结构 (tipcs2220m000)
为通用物料生成产品结构时,将选中物料 (tcibd0501m000)进程中所生成物料数据的定制复选框。
如果选中了“物料 (tcibd0501m000)”进程中所生成物料的具有 PCS 复选框,则在 PCS项目中生成产品结构。
- 重新生成现有产品变型结构
-
如果选中此复选框,则现有产品变型结构将被删除并生成一个新的产品变型结构。 此操作可更新现有销售订单行和销售报价单行。
如果清除此复选框,则生成一个新的产品变型结构。
- 物料
-
An item produced on a customer specification for a specific project. A customized item can have a customized BOM and/or a customized routing and is normally not available as a standard item. A customized item can, however, be derived from a standard item or a generic item.
- 通用物料
-
An item that exists in multiple product variants. Before any manufacturing activities are performed on a generic item, the item must be configured to determine the desired product variant.
示例
Generic item: electric drill
Options:
- 3 power sources (batteries, 12 V or 220 V)
- 2 colors (blue, gray).
A total of 6 product variants can be produced with these options.
- 产品变型
-
可以在此字段中选择产品变型。
- 项目
-
A collection of manufacturing and purchasing actions that are performed for a particular customer order. A project is initiated to plan and coordinate the production of the to be manufactured items.
For a standard-to-order production, the project is only used to link the item with the customer order. A project can also include these:
- Customized item data (BOMs and routings)
- Project planning (activity planning)
- 参考日期
-
生成定制产品结构时分解物料清单 (BOM) 和工艺流程工序的日期。
- 更新项目参考日期
-
如果选中此复选框,则项目的参考日期将更新为此进程中的参考日期。
如果清除此复选框,则项目的参考日期不会更新为此进程中的参考日期。
- 生成方法
-
通过此字段,您可以指定用于生成项目结构的方法。
允许值
您可以选择以下方法:
-
“按订单设计”
LN 生成物料的产品结构,包括定制物料、定制物料清单 (BOM) 以及定制工艺流程。 -
“标准按订单生产”
LN 创建物料的项目控制模块 (PCS) 项目,但不创建定制物料清单 (BOM) 及工艺流程。 项目控制模块 (PCS) 项目主要用于挂钩目的,例如跟踪定制物料的成本。
注意对于通用物料,LN 将为项目结构的通用构成创建项目控制模块 (PCS) 项目、定制物料清单 (BOM) 以及定制工艺流程。 但对于具有生产物料清单 (BOM) 的物料结构(较低层次)的构成,物料将成为定制物料,但不会生成定制物料清单 (BOM) 及工艺流程。
-
- 检查标准物料库存
-
如果选中此复选框,将检查标准物料的库存级别。 如果标准物料的库存充足,则不会生成定制物料。 如果没有库存或库存不足,则会生成定制物料。
- 更新价格报价单行
-
如果选中此复选框,将更新现有报价单行中的价格。
- 更新价格销售订单行
-
如果选中此复选框,将更新现有销售订单行中的价格。
- 打印警告
-
如果选中此复选框,则打印执行进程期间发生的任何警告。