Inspection Lines to be Split (whinh2131m400)

Use this session to specify the lines and quantities to split.

Note: 
  • This session can be accessed from the Lines option in the Split Inspection (whinh2231m200) session. However, the Split Inspection (whinh2231m200) session can be accessed using the Split Inspection option on the Action menu in the following sessions:
    • Warehouse Inspection (whing3622m000)
    • Inspection Lines (whinh2131m000)
  • The Split Inspection option is displayed only if the status of the warehouse inspection is Open.

Field Information

Inspection
The inspection number for which the split inspection is to be created.
Inspection Sequence
The sequence number of the inbound or outbound inspection.
Inspection Status

The status of the inspection.

Allowed values

Open

The items are ready (blocked) for inspection. The user can specify the approved, rejected or (inbound and inventory only) destroyed quantities and process the inspection and inspection lines.

In Process

New inspection lines cannot be added to the inspection. The user can insert the approved, rejected or destroyed quantities and process the inspection and inspection lines.

An inspection obtains the In Process status if:

  • The user saves inspection results for an inspection line of the inspection.
  • The user clicks Set In Process for the selected inspection.

    The Set In Process option is available in these sessions:

    • Warehouse Inventory Inspections Overview (whinh3122m200)
    • Warehouse Inspections Overview (whinh3122m000)
    • Warehouse Inspection (whinh3622m000)
    • Warehouse Inventory Inspection (whinh3622m200)
    • Warehouse Inspections (whinh2631m100)
  • Quality is implemented, and Quality is leading, the Warehousing inspection is set in process after the Quality inspection is set in process.
Processed

The inspection or inspection line is finalized. The items listed on the inspection are approved, rejected or (inbound and inventory only) destroyed.

Advised

Inbound advice to the storage location is created for the approved and processed inspection. This status is used for the inbound flow.

Put Away

The inbound advice and/or the storage list of the approved and processed inspection are put away and the goods are stored in the storage location. This status is used for the inbound flow.

Item
The code of the item for which the inspection is performed.
Stock Point
Inspection Line
The inspection line created for the inspected stock point detail.
Lot
The lot code.
Serial Number
The serial number of the item.
Quantity To be Inspected
The number of items to be inspected.
Storage Unit
The unit in which the quantity of stored goods is expressed.
Move Inspection Line
If this check box is selected, the inspection line is moved to another line.
Note: You can select this check box only if there are more than one inspection line.
Quantity To be Split
The quantity of items to be split that is available in the storage unit.
Note: This field is enabled only if the status of the inspection is open and Move Inspection Line check box is cleared.
Rental Owner
The name of the rental owner for whom the Inspection line is split.
Inventory Date
The inventory date of the item to be inspected.
Effectivity Unit
The code of the effectivity unit.
E-item Revision
The number of engineering item revision.
Manufacturer
The manufacturer of the inspected item.
Manufacturer Part Number
The manufacturer part number (MPN) of the inspected item.
Inspection Location
Warehouse
The code of the warehouse.
Location
The location of the warehouse.