Check Material Availability (tstdm2220m000)
Use this batch session to calculate Material Availability for a range of orders. The results of this check can be viewed in Service Material Availability (tstdm2520m000) session.
Field Information
- Start Date
-
The From and To fields define a range of: Planned Start Time.
- Finish Date
-
The From and To fields define a range of: Planned Finish Time.
- Order Date
-
The From and To fields define a range of: order creation dates.
- Sold-to Business Partner
-
The From and To fields define a range of: sold-to business partners.
- Service Type
-
The From and To fields define a range of: service types on the order.
- Order Origin
-
The From and To fields define a range of: origins of the Order.
Allowed values
- Service Order
- Maintenance Sales Order
- Work Order
- Order
-
The From and To fields define a range of: service/work/maintenance sales order numbers.
Note: The from and to fields must be set to the same order origin. - Activity Line
-
The From and To fields define a range of: activity line numbers.
Note: The order origin of the From and To fields must be the same. - Material Line
-
The From and To fields define a range of: material line numbers.
Note: The order origin of the From and To fields must be the same. - Order Status
-
The From and To fields define a range of: status of the order.
- Check Planned Inventory
-
If this check box is selected, the Planned Inventory check is performed.
- Check On Hand Inventory
-
If this check box is selected, the On-Hand Inventory check is performed.
- Scope of Inventory Check
-
The locations where the material availability can be checked.
Allowed values
- All Warehouses in Planning Cluster
-
Checks if the material is available in the warehouse defined on the Material Line.
- Current Warehouse Only
-
Checks if the material is available in one of the warehouses in the same cluster as the warehouse defined on the Material Line.
- Update Planned Delivery Time of Material Lines
-
If this check box is selected, the Planned Delivery Time of the Material Lines is updated with the Planned Available Date when Inventory Check Status is set to Supply is late in the Service Material Availability (tstdm2520m000) session. When this check box is selected and the Check Planned Inventory check box is also selected, this check is recalculated after the update.
- Update Activities and Orders with Latest Planned Material Line
-
If this check box is selected, the Planned Start time of the orders and the activities of the related material line, are updated with the latest Planned Delivery time of the material lines..
- Synchronize Materials with Latest Planned Material Line
-
If this check box is selected, the Planned Delivery time of all material lines belonging to the order or activity are updated with the last Planned Delivery time of the material lines.
- Orders with Shortages
-
If this check box is selected, LN generates reports for the orders with the Inventory Check Status set to Shortage or Supply is late.
- Orders without Shortages
-
If this check box is selected, LN generates reports for the orders with the Inventory Check Status set to a value other than Available.