Territory and Preferred Engineer Planning (tsspc4600m000)

Use this session to specify the data for territory and preferred engineer planning.

Field Information

General
Territory Planning

The unique ID of territory planning.

Description

The description or name of the code.

Text

If this check box is selected, a text is present.

Number of Visits

The number of visits of the service engineer in a day.

Unit

The unit in which the number of visits is expressed.

Capacity Allocations Calculated On

The date and time when the capacity allocations is calculated.

Required Capacity
Number of Serialized Items

The number of the serialized item to be used for territory planning.

Unassigned

The number of serialized item that is not assigned to available capacity.

Note: If calculation run is not executed, the value in this field is the same as the number of serialized items.
Planned Activities

The total time of the planned activities.

Unit

The unit in which the total time is expressed.

Visits

The total number of planned activity visits by the service engineer.

Service Orders

The total amount of time required to execute the service orders.

Visits

The total number of visits by the service engineer for the service orders.

Unexpected Workload

The total time of the unexpected workload for the service engineer.

Visits

The number of unexpected visits by the service engineer.

Expected Travel Time

The total time of the expected travel of the service engineer calculated by LN.

Total Capacity

The total capacity of the available resources.

Visits

The number of visits by the service engineer.

Available Capacity
Number of Resources

The total number available resources.

Employee Calendar Range

This field is displayed only if determine capacity field is set to employee calendar.

This field is displayed only if determine capacity field is set from employee calendar.

Available Capacity

The total available capacity of all the resources.

Workload

The total workload of the required capacities that can be assigned to available capacity.

Travel Time

The total travel time of the resources calculated by LN.

Free Capacity

LN calculates the free capacity as follows:

Free Capacity = Available capacity - Assigned Work Load - Calculated travel Time.