Set High Level Available Capacity (tsspc4220m000)
Use this session to generate simulation capacities with an available capacity.
Field Information
- Territory Planning
-
The unique ID of the territory planning for which high level available capacity is set.
- Description
-
The description or name of the code.
- Number of Available Capacities
-
The number of available capacities you want to create.
- Capacity (Days)
-
The number of days assigned to a simulation capacity.
- Unit for Day
-
The unit in which the capacity (days) is expressed.
- Working Time per Day
-
The working time in a day for a simulation capacity.
- Unit
-
The unit in which the working time is expressed.
- Capacity
-
The capacity in time duration for a simulation.
LN calculates the capacity as follows:
Capacity = Capacity (Days) * Working Time Per Day
- Time Duration Unit
-
The unit in which the capacity is expressed.
- Total Capacity
-
The total capacity of the simulation.
- Remove Existing Available Capacities
-
If this check box is selected, LN clears the existing available capacities before the new simulation capacities are created. If, for the existing available capacities, the Capacity Allocation run has been executed, LN clears the value of all the calculated fields.