Activity Set for Job Shop Orders (tsspc3610m600)

Use this session to view the details of activity set lines for the Job Shop Orders.

Note: 
  • This session is displayed only if the Group Planning for Job Shop Orders Implemented is selected.
  • The Plan Groups and Activity Sets option is displayed, only if the Planned by Origin check box for the job shop orders is cleared on the Manufacturing tab in the Resource Planning Parameters (tsspc0101m000) session.

Field Information

Group

The unique ID of the group.

Allocated Resource

The assigned resource of the specified group planning.

Activity Set

The group planning activity set number.

Activity Set Sequence

The sequence number of the group planning activity set.

Activity Set Status

The status of the activity set.

Allowed values

Created

The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.

Planned

The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.

Not Planned

The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.

Released

The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.

Maximum Operation Status

The highest possible status of all the operations in the group.

Allowed values

Planned

The status when the plan is created.

Ready to Start

When there is enough Quantity Completed on all the previous operations to report complete the minimum order quantity of the operation in the Report Operations Completed (tisfc0130m000) session, the operation status is set to Ready to Start by the previous operation.

Started

If you use LN the operation status is Started when any quantity is reported as completed in Job Shop Control .

Active

A WIP transaction has been performed on this operation. When the first operation is set to Active, the order status becomes Active too.

Blocked

The operation has been blocked in Job Shop Control by the user or by an inspection order. Refer to Blocking operations.

Completed

All the work has been completed for the operation. The quantities reported as completed and rejected are final. You can set this status in the Report Operations Completed (tisfc0130m000) details session. If required, you can click Reset Operation Status in the Report Operations Completed (tisfc0130m000) details session to change the operation status from Completed back to Active.

Closed

The financial results of the operation have been calculated. Operations can only be closed in LN.

Firm Planned

If this check box is selected, the group is firm planned. That is, you cannot change the start and finish date of the group.

Frozen

If this check box is selected, you cannot add new groups to the existing groups.

Keep Sequence of Activities

If this check box is selected, LN does not change the sequence of the activities when the specified activity set is planned.

Sort Method

The sorting method for the job shop order activities in an activity set.

Allowed values

Earliest Start
Latest Finish
Latest Start
Planned Start
Planned Finish
Original Group

The planning group number from which the activity sets are originating.

Original Activity Set

The planning activity set number from which the activity sets are originating.

Planned Start Time

The start date and time of the first activity sets in the specified group.

Planned Finish Time

The finish date and time of the last activity sets in the specified group.

Total Activity Duration

The cumulative activity duration of activity sets in the group.

Time Duration Unit

The unit in which the total activity duration is expressed.