Activity Set for Work Orders (tsspc3610m100)

Use this session to view the details of activity set lines for work orders.

Note: The Plan Groups and Activity Sets option is displayed, only if the Planned by Origin check box is cleared on the Work Orders tab in the Resource Planning Parameters (tsspc0101m000) session.

Field Information

Group

The unique ID of the group.

Allocated Resource

The assigned resource of the specified group planning.

Activity Set

The group planning activity set number.

Activity Set Sequence

The sequence number of the group planning activity set.

Sort Method

The sorting method for work order activities in an activity set.

Allowed values

Earliest Start
Latest Finish
Latest Start
Planned Start
Planned Finish
Frozen

If this check box is selected, you cannot add new groups to the existing groups.

Firm Planned

If this check box is selected, the group is firm planned. That is, you cannot change the start and finish date of the group.

Keep Sequence of Activities

If this check box is selected, LN does not change the sequence of the activities when the specified group is planned.

Original Group

The planning group number from which the activity sets are originating.

Original Activity Set

The planning activity set number from which the activity sets are originating.

Planned Start Time

The start date and time of the first activity sets in the specified group.

Planned Finish Time

The finish date and time of the last activity sets in the specified group.

Total Activity Duration

The cumulative activity duration of activity sets in the group.

Time Duration Unit

The unit in which the total activity duration is expressed.