Group for Corrective Action Plans (tsspc3600m801)
Use this session to review and maintain the group planning data of a specific Corrective Action Plan.
Field Information
- Group
-
The unique ID of the group.
- Group Status
-
The least possible status of all the activities in the group.
Allowed values
- Created
-
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
- Planned
-
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
- Not Planned
-
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
- Released
-
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
- Maximum Activity Status
-
The highest possible status of all the activities in the group.
Allowed values
- Open
- Approved
- In Progress
- Completed
- Closed
- Canceled
- Frozen
-
If this check box is selected, the group is frozen and you cannot add new activity sets to the existing groups.
- Firm Planned
-
If this check box is selected, the group is firm planned and you cannot change the start and finish date of the group.
- Sort Method
-
The sorting method for Non-Conformance Report activities in an activity set.
Allowed values
- Earliest Start
- Latest Finish
- Latest Start
- Planned Start
- Planned Finish
- Keep Sequence of Activity Sets
-
If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned.
- Check Resources for Attribute Values
-
If this check box is selected, LN allocates resources for Corrective Action Plans based on attribute values.
- Check Resources for Skills
-
If this check box is selected, LN allocates resources for Corrective Action Plans, based on skills.
- Check Resources for Availability
-
If this check box is selected, LN checks availability of resources for Corrective Action Plans.
- Minimum Availability Percentage
-
The minimum availability percentage of the resource for the allocation.
- Allocated Resource
-
The engineers allocated to the specified group.
- Planned Start Time
-
The earliest start date and time of all activities in the specified group.
- Planned Finish Time
-
The latest finish date and time of all activities in the specified group.
- Plan Method
-
The method to plan the service order activities.
Allowed values
- Planning Based on Time
- Planning Based on Route
- Total Activity Duration
-
The cumulative duration of activities for all the activity sets in the group.
- Time Duration Unit
-
The unit in which the total activity duration is expressed.