Group for Projects (tsspc3600m700)
Use this session to view and maintain the groups created for Project.
- This session is displayed only if the Group Planning for Projects Implemented check box is selected in the Resource Planning Parameters (tsspc0101m000) session.
- The Plan Groups and Activity Sets option is displayed, only if the Planned by Origin check box is cleared on the Projects tab in the Resource Planning Parameters (tsspc0101m000) session.
Field Information
- Group
-
The unique ID of the group.
- Group Status
-
The least possible status of all the activities in the group.
- Maximum Activity Status
-
The highest possible status of the project activity that is assigned to the group.
- Frozen
-
If this check box is selected, the group is frozen and you cannot add new activity sets to the existing groups.
- Firm Planned
-
If this check box is selected, the group is firm planned and you cannot change the start and finish date of the group.
- Sort Method
-
The sorting method for service order activities in an activity set.
Allowed values
- Earliest Start
- Latest Finish
- Latest Start
- Planned Start
- Planned Finish
- Keep Sequence of Activity Sets
-
If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned.
- Check Resources for Attribute Values
-
If this check box is selected, LN allocates resources for service orders based on attribute values.
- Check Resources for Skills
-
If this check box is selected, LN allocates resources for service orders, based on skills.
- Check Resources for Availability
-
If this check box is selected, LN checks availability of resources for service order.
- Minimum Availability Percentage
-
The minimum availability percentage of the resource for the allocation.
- Allocated Resource
-
The resources assigned to the specified group.
- Planned Start Time
-
The earliest start date and time of all activities in the specified group.
- Planned Finish Time
-
The latest finish date and time of all activities in the specified group.
- Respect Earliest Start Time
-
If this check box is selected, LN considers the earliest start time to plan the project activities.
- Respect Latest Finish Time
-
If this check box is selected, LN considers the latest finish time to plan the planned activities.
- Total Activity Duration
-
The cumulative duration of activities for all the activity sets in the group.
- Time Duration Unit
-
The unit in which the total activity duration is expressed.
- Start Travelling on Start Time
-
If this check box is selected, the engineer must start travelling to the location where the activity must be performed, at the Planned Start Time specified for a project. If this check box is cleared, the engineer must reach the location early and start working on the activity at the specified Planned Start Time.
Note: This field is enabled only if the Plan Method set to Planning Based on Route. - Total Travel Duration
-
The cumulative duration of travel for all the activity sets in the group.
- Total Travel Distance
-
The cumulative travel distance of all the activity sets in the group.
- Distance Unit
-
The unit in which the travel distance is expressed
- Plan Method
-
The method to plan the project activities.
Allowed values
- Planning Based on Time
- Planning Based on Route
- Start Address of Route
-
The address of the starting point of the route.
Allowed values
- Not Applicable
- At First Activity
- At Company Address
- At Department Address
- At Employee Home Address
Note: This field is enabled only if the Plan Method field is set to Planning Based on Route. - Distance Calculation Method
-
The method used to recalculate distance.
Allowed values
- As the crow flies
- Bing Maps
- Google Maps
- Not Applicable
- Average Travel Speed
-
The average travel speed used to calculate travel time when planning a route.
Note: This field is enabled only if the Plan Method field is set to Planning Based on Route. - Unit
-
The unit in which the average travel speed is expressed.
- Travel Offset Time
-
The time used to calculate travel time when planning a route.
Note: This field is applicable only if Plan Method is set to Planning Based on Route.