Group for Work Orders (tsspc3600m100)

Use this session to view data of a specific work order group and an overview of all related data.

The tabs refer to the following sessions:

  • Activity Sets: Activity Set - Lines for Work Orders (tsspc3610m100) session.
  • Activities: Work Order - Lines (tswcs2100m100) session.
  • Proposed Resources: Proposed Resources (tsspc3604m300) session.
  • Resources: Group Planning Group – Resources (tsspc3102m000) session.
  • Attribute Values: Group Planning Group – Attribute Values (tsspc3101m000) session.
  • Set - Attributes Values: Activity Sets - Attributes Values (tsspc3111m000) session.
  • Skills:
  • Message Log: Message Log (tcstl1500m000) session.
Note: The Plan Groups and Activity Sets option is displayed, only if the Planned by Origin check box is cleared on the Work Orders tab in the Resource Planning Parameters (tsspc0101m000) session.

Field Information

Group

The unique ID of the group.

Frozen

If this check box is selected, the group is frozen and you cannot add new groups to the existing groups.

Firm Planned

If this check box is selected, the group is firm planned and you cannot change the start and finish date of the group.

Keep Sequence of Activity Sets

If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned.

Sort Method

The sorting method for work order activities in an activity set.

Allowed values

Earliest Start
Latest Finish
Latest Start
Planned Start
Planned Finish
Allocated Resource

The resources assigned to the specified group. Assigned resources are copied from group planning to the service order activity, work order activity or planned activity.

Check Resources for Skills

If this check box is selected, LN allocates resources for work orders, based on skills.

Check Resources for Attribute Values

If this check box is selected, LN allocates resources for work orders based on attribute values.

Check Resources for Availability

If this check box is selected, LN checks availability of resources for work order.

Minimum Availability Percentage

The minimum availability percentage of the resource for the allocation.

Planned Start Time

The start date and time of the first activity set in the specified group.

Planned Finish Time

The finish date and time of the last activity set in the specified group.

Plan Method

The method to plan the work order activities.

Allowed values

Planning Based on Time
Planning Based on Route
Respect Earliest Start Time

If this check box is selected, LN considers the earliest start time to plan the work order activities.

Note: For a work order activity, the planned start time must not be planned after the earliest start time.
Respect Latest Finish Time

If this check box is selected, LN considers the latest finish time to plan the work order activities. The Planned Finish Time cannot be planned after the Latest Finish Time. The work order activity is not planned.

Note: LN re-plans the route for the activity.
Respect Material Availability Date

If this check box is selected, LN considers the Material Availability Date specified for the work orders in the Resource Planning Parameters (tsspc0101m000) session, to schedule the work order activities in a Group.

Note: 
  • This field is visible only if the Check Material Availability check box in the Service Order Parameters (tssoc0100m000) session or the Check Material Availability check box in the Work Order Parameters (tswcs0100m000) session is selected.
  • This field is disabled if the Firm Planned check box is selected.