Group for Service Orders (tsspc3600m000)
Use this session to review and maintain the group planning data of a specific service order.
The tabs refer to the following sessions:
- Activity Sets: Activity Set - Lines for Service Orders (tsspc3610m000) session.
- Activities: Service Order Activity - Lines (tssoc2110m100) session.
- Proposed Resources: Proposed Resources (tsspc3604m300) session.
- Resources: Group Planning Group – Resources (tsspc3102m000) session.
- Attribute Values: Group Planning Group – Attribute Values (tsspc3101m000) session.
- Set - Attributes Values: Activity Sets - Attributes Values (tsspc3111m000) session.
- Skills: Group - Skills (tsspc3103m000) session.
- Message Log: Message Log (tcstl1500m000) session.
Field Information
- Group
-
The unique ID of the group.
- Frozen
-
If this check box is selected, the group is frozen and you cannot add new activity sets to the existing groups.
- Firm Planned
-
If this check box is selected, the group is firm planned and you cannot change the start and finish date of the group.
- Keep Sequence of Activity Sets
-
If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned.
- Sort Method
-
The sorting method for service order activities in an activity set.
Allowed values
- Earliest Start
- Latest Finish
- Latest Start
- Planned Start
- Planned Finish
- Allocated Resource
-
The engineers assigned to the specified group. Assigned engineers are copied from group planning to the service order activity.
- Check Resources for Skills
-
If this check box is selected, LN allocates resources for service orders, based on skills.
- Check Resources for Attribute Values
-
If this check box is selected, LN allocates resources for service orders based on attribute values.
- Check Resources for Availability
-
If this check box is selected, LN checks availability of resources for service order.
- Minimum Availability Percentage
-
The minimum availability percentage of the resource for the allocation.
- Planned Start Time
-
The earliest start date and time of all activities in the specified group.
- Planned Finish Time
-
The latest finish date and time of all activities in the specified group.
- Plan Method
-
The method to plan the service order activities.
Allowed values
- Planning Based on Time
- Planning Based on Route
- Distance Calculation Method
-
The method used to recalculate distance.
Allowed values
- Crow Based
-
The distance is calculated "as the crow flies" and from this distance the travel time is calculated with the information of the average travel speed towards the location of serialized item.
- Road Based Distance Only
-
The distance is calculated with the type of website you select in the provider field in the Service Planning Parameters (tsspc0100m000) session.
- Road Based Distance and Travel Time
-
The distance and the travel time are calculated with the type of website you select in the provider field in the Service Planning Parameters (tsspc0100m000) session
- Start Address of Route
-
The address of the starting point of the route.
Allowed values
- Not Applicable
- At First Activity
- At Company Address
- At Department Address
- At Employee Home Address
Note: This field is enabled only if the Plan Method field is set to Planning Based on Route. - Average Travel Speed
-
The average travel speed used to calculate travel time when planning a route.
Note: This field is enabled only if the Plan Method field is set to Planning Based on Route. - Unit
-
The unit in which the average travel speed is expressed.
- Travel Offset Time
-
The time used to calculate travel time when planning a route.
Note: This field is applicable only if plan method is set to Planning based on route. - Start Travelling on Start Time
-
If this check box is selected, the engineer must start travelling to the location, where the activity must be performed, at the Planned Start Time specified for a service order. If this check box is cleared, the engineer must travel to the location in advance and start working on the activity at the specified Planned Start Time.
Note: This field is enabled only if the Plan Method is set to Planning Based on Route. - Time Duration Unit
-
The unit in which the travel offset time is expressed.
- Respect Earliest Start Time
-
If this check box is selected, LN considers the earliest start time to plan the service order activities.
Note: For a service order activity, the planned start time must not be planned after the earliest start time. - Respect Latest Finish Time
-
If this check box is selected, LN considers the latest finish time to plan the planned activities. The Planned Finish Time cannot be planned after the Latest Finish Time. The service order activity is not planned.
Note: LN re-plans the route for the activity. - Respect Material Availability Date
-
If this check box is selected, LN considers the Material Availability Date specified for the service orders in the Resource Planning Parameters (tsspc0101m000) session, to schedule the service order activities in a Group.
Note:- This field is visible only if the Check Material Availability check box in the Service Order Parameters (tssoc0100m000) session or the Check Material Availability check box in the Work Order Parameters (tswcs0100m000) session is selected.
- This field is disabled if the Firm Planned check box is selected.