Groups for Corrective Action Plans for Dashboard (tsspc3500m500)
Use this session to view and modify group planning data for corrective action plans.
Field Information
- Start Date
-
The start date of the group. LN displays the details of the groups with a start date later than the specified date.
- End Date
-
The finish date of the group. LN displays the details of the groups with a finish date earlier than the specified date.
- Allocated Resource
-
The resources allocated to the specified group. The allocated resources are copied from group planning to the corrective action plan.
- Group
-
The unique ID of the group.
- Allocated Resource
-
The resources allocated to the specified group. The allocated resources are copied from group planning to the corrective action plan.
- Group Status
-
The least possible status of all the activities in the group.
Allowed values
- Created
-
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
- Planned
-
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
- Not Planned
-
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
- Released
-
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
- Frozen
-
If this check box is selected, the group is frozen and you cannot add new groups to the existing groups.
- Firm Planned
-
If this check box is selected, the group is firm planned and you cannot change the start and finish date of the group.
- Planned Start Time
-
The planned start date and time of the first activity set in the specified group.
- Planned Finish Time
-
The planned finish date and time of the last activity set in the specified group.
- Sort Method
-
The sorting method for activities in an activity set.
Allowed values
- Earliest Start
- Latest Finish
- Latest Start
- Planned Start
- Planned Finish
Note:- This value is defaulted from the Group Sets for Quality (tsspc2190m400) session, if the group is part of the group set.
- If group is not part of a group set, this value is defaulted from Sort Method specified in the Service Planning Parameters (tsspc0100m000) session.
- Keep Sequence of Activity Sets
-
If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned.
Note: This value is defaulted from the Group Sets for Quality (tsspc2190m400) session. - Total Activity Duration
-
The cumulative duration of activities for all the activity sets in the group.