Group Planning Planboard (tsspc3260m000)
Use this session to display the selected groups and activities in a Gantt chart.
You can also start the Gantt chart using the form command View Gantt Chart in several Group Planning sessions.
The Gantt chart can be displayed in two modes:
- Gantt view: Groups and activities are displayed based on the characteristics. In this view, each group/group activity can be moved in time. All activities and groups after the shifted group/group/activity are re-planned.
- Schedule view: Groups or Activities are displayed based on the assigned resource. In this view, a group or activity can be moved to a different resource. If an activity is moved, all activities and groups of the same group are re-assigned.