Activities for Corrective Action Plans (tsspc3120m500)

Use this session to view and maintain activities of Corrective Action Plans.

Field Information

Group

The unique ID of the group.

Planning Sequence

The planning sequence of the activity sets for the Corrective Action Plans.

Activity Set

The group planning activity set number for the Corrective Action Plans.

Start Date Activities

The start date and time of the activities that must be displayed.

Finish Date Activities

The finish date and time of the activities that must be displayed.

Moved Activities

If this check box is selected, LN displays the activity that have been moved from another group.

Allocated Resource

The engineer allocated to the specified group.

Activity Set Attributes

The attributes of the activity set.

Line

The group planning activity number.

Sequence

The group planning activity sequence.

Status

The status of the activity.

Allowed values

Created

The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.

Planned

The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.

Not Planned

The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.

Released

The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.

Description

The description or name of the code.

Status

The status of the activity.

Allowed values

Open
Approved
In Progress
Completed
Closed
Canceled
Firm Planned

If this check box is selected, the activity is firm planned and you cannot change the start and finish date of the activity.

Planned Start Time

The start date and time of the group planning activity.

Planned Finish Time

The finish date and time of the group planning activity.

Activity Duration

The duration of the Corrective Action Plan activity.

Calendar

The calendar that is used to plan Corrective Action Plan related activities.

Description

The description or name of the code.

Availability Type

The availability type which is used to calculate the start and finish time of the activities to be performed in each location.

Description

The description or name of the code.

Time Zone

The time zone that belongs to the specified calendar.

Description

The description or name of the code.

Group

The planning group number from which the activities are originating.

Activity Set

The planning activity set number from which the activities are originating.

Activity Line

The planning activity number from which the activities are originating.