Activities for Corrective Action Plans (tsspc3120m500)
Use this session to view and maintain activities of Corrective Action Plans.
Field Information
- Group
-
The unique ID of the group.
- Planning Sequence
-
The planning sequence of the activity sets for the Corrective Action Plans.
- Activity Set
-
The group planning activity set number for the Corrective Action Plans.
- Start Date Activities
-
The start date and time of the activities that must be displayed.
- Finish Date Activities
-
The finish date and time of the activities that must be displayed.
- Moved Activities
-
If this check box is selected, LN displays the activity that have been moved from another group.
- Allocated Resource
-
The engineer allocated to the specified group.
- Activity Set Attributes
-
The attributes of the activity set.
- Line
-
The group planning activity number.
- Sequence
-
The group planning activity sequence.
- Status
-
The status of the activity.
Allowed values
- Created
-
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
- Planned
-
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
- Not Planned
-
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
- Released
-
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
- Description
-
The description or name of the code.
- Status
-
The status of the activity.
Allowed values
- Open
- Approved
- In Progress
- Completed
- Closed
- Canceled
- Firm Planned
-
If this check box is selected, the activity is firm planned and you cannot change the start and finish date of the activity.
- Planned Start Time
-
The start date and time of the group planning activity.
- Planned Finish Time
-
The finish date and time of the group planning activity.
- Activity Duration
-
The duration of the Corrective Action Plan activity.
- Calendar
-
The calendar that is used to plan Corrective Action Plan related activities.
- Description
-
The description or name of the code.
- Availability Type
-
The availability type which is used to calculate the start and finish time of the activities to be performed in each location.
- Description
-
The description or name of the code.
- Time Zone
-
The time zone that belongs to the specified calendar.
- Description
-
The description or name of the code.
- Group
-
The planning group number from which the activities are originating.
- Activity Set
-
The planning activity set number from which the activities are originating.
- Activity Line
-
The planning activity number from which the activities are originating.