Activities for Work Orders (tsspc3120m100)

Use this session to view and maintain activities of work order.

Field Information

Group

The unique ID of the group.

Planning Sequence

The planning sequence of the activity sets for the work order.

Activity Set

The group planning activity set number.

Start Date Activities

The start date and time of the activities that must be displayed.

Finish Date Activities

The finish date and time of the activities that must be displayed.

Moved Activities

If this check box is selected, LN displays the activity that is moved from another group.

Allocated Resource

The assigned department of the specified group .

Activity Set Attributes

The attributes of the activity set.

Activity Line

The group planning activity number.

Activity Sequence

The group planning activity sequence.

Activity Status

The status of the activity.

Allowed values

Planned
Released
Completed
Signed-Off
Closed
Canceled
Free
Work Order

The work order activity number.

Activity Line

The description or name of the code.

Description

The description or name of the code.

Work Order Activity Status

The status of the activity.

Allowed values

Planned
Released
Completed
Signed-Off
Closed
Canceled
Free
Firm Planned

If this check box is selected, the group is firm planned. That is, you cannot change the start and finish date of the group.

Appointment

If this check box is selected, appointment for the work order activity is made.

Planned Start Time

The start date and time for the group planning activity.

Planned Finish Time

The finish date and time for the group planning activity. .

Earliest Start Time

The earliest start time of the work order activity.

Latest Finish Time

The latest finish time of the work order activity.

Queue Time

The queue time for work order activity.

Activity Duration

The duration of the work order activity.

Calendar

The calendar that is used to plan work order activities.

Description

The description or name of the code.

Availability Type

The availability type which is used to calculate the start and finish time of the activities to be performed in each location.

Description

The description or name of the code.

Time Zone

The time zone that belongs to the specified calendar.

Description

The description or name of the code.

Original Group

The planning group number from which the activities are originating.

Original Activity Set

The planning activity set number from which the activities are originating.

Material Availability Date

The date LN refers to, for the material availability check in group planning, for the work orders. The date can be ATP date, the Planned Inventory Date or the Required Delivery date.

Note: 
  • LN defaults this value from the Material Availability Date specified for the work orders in the Resource Planning Parameters (tsspc0101m000) session.
  • This field is visible only if the Check Material Availability check box in the Service Order Parameters (tssoc0100m000) session or the Check Material Availability check box in the Work Order Parameters (tswcs0100m000) session is selected.