Activity Sets for Projects (tsspc3110m300)

Use this session to view and maintain group planning groups generated from group planning activity sets for projects.

Note: 
  • This session is displayed only if the Group Planning for Projects Implemented check box is selected in the Resource Planning Parameters (tsspc0101m000) session.
  • The Plan Groups and Activity Sets option is displayed, only if the Planned by Origin check box is cleared on the Projects tab in the Resource Planning Parameters (tsspc0101m000) session.

Field Information

Group

The unique ID of the group.

Allocated Resource

The resource assigned to the specified group. Assigned resources are copied from group planning to the project activity.

Start Date Activity Sets

The start date of the activity set. LN displays the activity sets with a start date later than the specified date.

Finish Date Activity Sets

The finish date of the activity set. LN displays the activity sets with a finish date earlier than the specified date.

Moved Activity Sets

If this check box is selected, LN displays the activity sets that have been moved from another group.

Activity Set

The group planning activity set number for the activity set.

Planning Sequence

The planning sequence of the activity set.

Activity Set Status

The status of the activity set.

Allowed values

Created

The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.

Planned

The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.

Not Planned

The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.

Released

The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.

Maximum Activity Status

The highest possible status of project that is assigned to the group.

Allowed values

Free
Actual
Final
Firm Planned

If this check box is selected, the activity set is firm planned and you cannot change the start and finish date of the activity set.

Frozen

If this check box is selected, the activity set is frozen and you cannot add new activities to the existing activity set.

Keep Sequence of Activities

If this check box is selected, LN does not change the sequence of the activities when the specified activity set is planned.

Planned Start Time

The start date and time of the first activity in the specified activity set.

Planned Finish Time

The finish date and time of the last activity in the specified activity set.

Sort Method

The sorting method for project activities in an activity set.

Allowed values

Earliest Start
Latest Finish
Latest Start
Planned Start
Planned Finish
Total Activity Duration

The cumulative duration of travel for all the activities in the activity set.

Total Travel Duration

The cumulative duration of travel for all the activities in the activity set .

Total Travel Distance

The cumulative distance of travel for all the activities in the activity set .

Original Group

The original planning group number.

Original Activity Set

The original activity set number.