Activity Sets for Work Orders (tsspc3110m100)
Use this session to view and maintain group planning groups generated from group planning activity sets for work orders.
Field Information
- Group
-
The unique ID of the group.
- Allocated Resource
-
The department assigned to the specified group. Assigned department are copied from group planning to the work order activity.
- Keep Sequence of Activities
-
If this check box is selected, LN does not change the sequence of the activities when the specified activity set is planned.
- Start Date Activity Sets
-
The start date of the activity set. LN displays the activity sets with a start date later than the specified date.
- Finish Date Activity Sets
-
The finish date of the activity set. LN displays the activity sets with a finish date earlier than the specified date.
- Moved Activity Sets
-
If this check box is selected, LN displays the activity sets that have been moved from another group.
- Activity Set
-
The group planning activity set number for the activity set .
- Planning Sequence
-
The planning sequence of the activity set .
- Firm Planned
-
If this check box is selected, the activity set is firm planned and you cannot change the start and finish date of the activity set.
- Frozen
-
If this check box is selected, the activity set is frozen and you cannot add new activities to the existing activity sets.
- Planned Start Time
-
The start date and time of the first activity in the specified activity set.
- Planned Finish Time
-
The finish date and time of the last activity in the specified activity set .
- Sort Method
-
The sorting method for service order activities in an activity set.
Allowed values
- Earliest Start
- Latest Finish
- Latest Start
- Planned Start
- Planned Finish
- Total Activity Duration
-
The cumulative duration of travel for all the activities in the activity set .
- Original Group
-
The original planning group number.
- Original Activity Set
-
The original activity set number.